Amendment of NSL-East Hi-Rise Residential Apartment

Amendment of NSL-East Hi-Rise Residential Apartment is a proposed residential project in Uppal, Medchal Malkajgiri, Telangana. It plans 1,248 units in 4 towers of up to 47 floors on 7 acres. Its stated project cost is ₹1,300 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 9 Jul 2025).

See it on the live map All projects in Medchal Malkajgiri

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is Amendment of NSL-East Hi-Rise Residential Apartment?

Amendment of NSL-East Hi-Rise Residential Apartment is a proposed residential project in Uppal, Medchal Malkajgiri, Telangana. It plans 1,248 units in 4 towers of up to 47 floors on 7 acres.

Who is building it?

The applicant is Nsl SEZ (Hyderabad) Private Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 9 Jul 2025), as of 27 Nov 2026.

Where is it?

In Uppal, Medchal Malkajgiri, Telangana.

How big is it?

It has a stated cost of ₹1,300 crore and a site of 7 acres.

When was it filed?

The application was filed on 2 Jun 2025.

Project details

StatusCleared for impact study
Status since9 Jul 2025
Application filed2 Jun 2025
Approval soughtEnvironmental approval
Application typeAmendment
SectorBuildings & townships
ApplicantNsl SEZ (Hyderabad) Private Limited
UseResidential
Units1,248
Towers4
Floors (tallest)47
Basements5
Height150 m
Land area7 acres (2.8 ha)
Built-up area4,48,007 m² (48,22,303 sq ft)
Plot area28,333 m² (3,04,974 sq ft)
Project cost₹1,300 crore
Village / localityUppal
Taluk / tehsilUppal
DistrictMedchal Malkajgiri
StateTelangana
Location fromSite boundary on record
Our referenceWID-TG-02614

In context

394 applications in Medchal Malkajgiri since January 2022 are in the same category (Buildings & townships): 300 approved, 54 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 7 acres, this one is larger than 57% of them.

28 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Uppal, Medchal Malkajgiri, Telangana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Nsl SEZ (Hyderabad) Private Limited in Medchal Malkajgiri

All 3 Nsl SEZ (Hyderabad) projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.