Quick answers
What is Mining project by M/s. KNR Constructions Ltd.,?
This approved mining project by M/s. KNR Constructions Ltd., is in Jaklair, Makthal, Narayanpet, Telangana. The site covers 3 acres.
Who is building it?
The applicant is Knr Constructions Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 11 Nov 2026), as of 27 Nov 2026.
Where is it?
In Jaklair, Makthal, Narayanpet, Telangana.
How big is it?
It has a stated cost of ₹31 lakh and a site of 3 acres.
When was it filed?
The application was filed on 30 Aug 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 11 Nov 2026 |
| Application filed | 30 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Knr Constructions Limited |
| Land area | 3 acres (1.2 ha) |
| Project cost | ₹31 lakh |
| Village / locality | Jaklair |
| Taluk / tehsil | Makthal |
| District | Narayanpet |
| State | Telangana |
| Location from | Site boundary on record |
| Our reference | WID-TG-03194 |
In context
36 applications in Narayanpet since January 2022 are in the same category (Mining): 25 approved, 2 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 3 acres, this one is smaller than 81% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Jaklair, Makthal, Narayanpet, Telangana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sri D.K. Bharath Simha Reddy — environmental approval granted, 2.1 km away
- Transfer of Environmental Clearance from Jurala Organic Farms & Agro… — environmental approval granted, 12.4 km away
- Transfer of Environmental Clearance from Jurala Organic Farms & Agro… — environmental approval granted, 12.4 km away
- Proposed to establish Synthetic Organic Chemicals manufacturing unit with… — cleared for impact study, 12.5 km away
- Proposed to establish Synthetic Organic Chemicals manufacturing unit with… — cleared for impact study, 12.5 km away
- Jurala Organic Farms & Agro Industries PVT. LTD., Unit-Ii — returned to applicant, 12.5 km away
- Mining project by M/s. P Manohar Reddy and Brothers Works Contractor — environmental approval granted, 14.9 km away
- Diversion Of 0.0381 Ha of Forest Land for Execution of T -Fiber Project… — forest land use approved, 18.8 km away
All 7 Knr Constructions projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.