Yes. Its status is “Environmental approval granted” (since 26 Sept 2026), as of 27 Nov 2026.
Where is it?
In Mokila, Shankarpalle, Ranga Reddy, Telangana.
How big is it?
It has a stated cost of ₹68.2 crore and a site of 1.2 acres.
When was it filed?
The application was filed on 14 Jul 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 26 Sept 2026 |
| Application filed | 14 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Savira Infra Projects |
| Use | Residential |
| Units | 75 |
| Towers | 1 |
| Floors (tallest) | 15 |
| Basements | 2 |
| Parking spaces | 300 |
| Land area | 1.2 acres (0.5 ha) |
| Built-up area | 29,445 m² (3,16,943 sq ft) |
| Plot area | 4,663 m² (50,192 sq ft) |
| Project cost | ₹68.2 crore |
| Village / locality | Mokila |
| Taluk / tehsil | Shankarpalle |
| District | Ranga Reddy |
| State | Telangana |
| Location from | Site boundary on record |
| Our reference | WID-TG-03217 |
What the filings say
Savira Infra Projects proposes to develop a residential apartment complex on a 0.47-hectare (1.15-acre) site in Mokila Village. The applicant's project report describes the development as a single residential tower consisting of two basement levels, a stilt floor, 15 upper floors, and a terrace.
What is planned
The project is designed as a high-rise residential building with a total height of 52.42 metres. The development will include 75 residential units, specifically 3 BHK apartments. The total built-up area is 29,445.12 square metres, which includes 22,184.67 square metres for the residential tower and 7,260.45 square metres for parking and services.
Project Components
| Item | Detail |
|---|---|
| Building Configuration | 2B + Stilt + 15 Floors + Terrace |
| Total Units | 75 (3 BHK) |
| Total Built-up Area | 29,445.12 sq.m |
| Ground Coverage | 1,392.00 sq.m (29.85%) |
| Greenbelt Area | 495.47 sq.m (10.62%) |
| Internal Roads & Others | 2,775.26 sq.m (59.53%) |
| Maximum Height | 52.42 m |
| Estimated Population | 450 persons |
Layout and design
The site plan shows a rectangular building footprint with 10-metre setbacks on all sides. The ground level includes two designated "Tot-lot" areas for recreation, measuring 178.83 square metres and 291.1 square metres respectively. A 30-metre wide main road provides access to the site.
Parking is distributed across the two basement levels and the stilt floor. The total parking area of 7,260.45 square metres is designed to accommodate 150 four-wheelers and 150 two-wheelers.
Water, power and access
The total water requirement is estimated at 67 kilolitres per day (KLD). Of this, 40.5 KLD will be fresh water sourced from groundwater or municipal supply. The remaining 26.5 KLD will be met through recycled treated water for flushing (24 KLD) and greenbelt irrigation (2.5 KLD).
Power demand is estimated at 509 kWh, to be supplied by the state electricity board. A 250 kVA diesel generator (DG) set will be installed for emergency backup. The site is located 1.3 km from the Kokapet–Shankarpally road and 5.5 km from the Shankarpally railway station.
Environmental safeguards
The applicant proposes to install an on-site Sewage Treatment Plant (STP) with a capacity of 65 KLD using Moving Bed Biofilm Reactor (MBBR) technology. Treated wastewater will be reused within the site, with a surplus of 22.1 KLD discharged into the municipal sewer line.
For solid waste management, the project is expected to generate 250 kg of domestic waste daily. This will be segregated into biodegradable waste (150 kg), which will be processed in an organic waste converter, and non-biodegradable waste (75 kg), to be sent to authorized vendors.
Stormwater management includes five rainwater percolation pits, each measuring 2m x 2m x 2m, located along the site boundary to recharge groundwater. The greenbelt will cover 10.62% of the plot area, featuring native tree species such as Mango, Neem, and Ashoka.
Timeline
The project is categorized as a B2 category building and construction project. According to the applicant's documentation, the environmental management plan budget includes ₹115 lakh for the construction phase and a recurring ₹16 lakh per year for the operational phase.
Construction of Residential Complex Project at Mokila Village, Shankarpally Mandal, RangaReddy District, Telangana State : SAVIRA INFRA PROJECTS site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
882 applications in Ranga Reddy since January 2022 are in the same category (Buildings & townships): 667 approved, 107 filed or under review, and 108 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1.2 acres, this one is smaller than 95% of them.
39 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mokila, Shankarpalle, Ranga Reddy, Telangana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Residential Apartment Project by M/s. Nikhila Constructions and Developers — initial checks, 250 m away
- Residential Apartments Construction Project located at Survey Nos.… — environmental approval granted, 700 m away
- Proposed Residential Villas named "Sark Prime North Meadows Two" by M/s. Sark… — environmental approval granted, 700 m away
- proposed Residential complex project - Sri Dhanvi Developers — environmental approval granted, 750 m away
- Proposed Mall and Multiplex Building named "The Mall of Mokila" by Mr. Syed… — environmental approval granted, 1 km away
- Amendment to the Environmental Clearance for the Construction of Residential… — environmental approval granted, 1.2 km away
- Proposed Residential Villas named "The Patio" by M/s. Praneeta Developers. — withdrawn, 1.3 km away
- Proposed Residential Villas named "The Patio" by M/s. Praneeta Developers. — environmental approval granted, 1.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.