| Official title | Proposed 160 KLPD Grain Based Distillery Project along with 4.6 MW Co-gen Power Plant and Zero Liquid Discharge (ZLD) unit by SPAC Starch Products India Private Limited at Mugasipudhur Village, Anthiyur Taluk, Erode District, Tamil Nadu. |
|---|---|
| Status | Environmental approval granted |
| Status since | 6 Oct 2022 |
| Application filed | 6 Oct 2022 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Spac Starch Products (India) Private Limited |
| Land area | 19.3 acres (7.8 ha) |
| Project cost | ₹231.1 crore |
| Village / locality | Mukasipudur |
| Taluk / tehsil | Bhavani |
| District | Erode |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-00185 |
In context
18 applications in Erode since January 2022 are in the same category (Industry): 13 approved, 4 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 19.3 acres, this one is larger than 56% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mukasipudur, Bhavani, Erode, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Kurichi "a" Village Gravel Mining Lease — environmental approval granted, 4.4 km away
- G.Parameshwaran Gravel Quarry Project Extent:4.67.0ha Nos.20/1, 20/2, 20/3,… — environmental approval granted, 5.2 km away
- Ammapettai Village Rough stone and Gravel Mining lease — under wildlife review, 6.2 km away
- Ammapettai Village Rough Stone and Gravel Mining Lease — lapsed, 6.2 km away
- AMMAPETTAI VILLAGE, Rough Stone and Gravel Quarry Project Belongs to Thiru.N.… — lapsed, 7.4 km away
- Tmt. T.M. Vijayalakshmi, Rough stone and Gravel Quarry, Extent of 0.76.5Ha… — environmental approval granted, 8.1 km away
- S. Madharasu Rough Stone Quarry S.F. No. 170 (Part - 4) over an extent of… — environmental approval granted, 10.9 km away
- S.Gokul Santhosh Rough Stone Quarry S.F. No. 170 (Part - 3) over an extent… — environmental approval granted, 11.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.