Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 31 Jan 2026 |
| Application filed | 25 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Buildings & townships |
| Applicant | Daimler India Commercial Vehicles Private Limited |
| Use | Industrial |
| Land area | 389.9 acres (157.8 ha) |
| Project cost | ₹68.9 crore |
| Village / locality | Orangadam |
| Taluk / tehsil | Sriperumbudur |
| District | Kanchipuram |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-02697 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 15 Jun 2026 | Environmental approval granted | 389.9 acres | ₹68.9 crore |
| Early planning filed 25 Nov 2025 (this page) | Cleared for impact study | 389.9 acres | ₹68.9 crore |
In context
219 applications in Kanchipuram since January 2022 are in the same category (Buildings & townships): 151 approved, 45 filed or under review, and 23 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 389.9 acres, this one is larger than 98% of them.
37 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Orangadam, Sriperumbudur, Kanchipuram, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Building project by Daimler India Commercial Vehicles Private Limited — environmental approval granted, 0 m away
- Oragadam — lapsed, 1.5 km away
- Construction of the Proposed New Industrial Shed — returned to applicant, 1.7 km away
- Laying of Underground Ofc Along Road Side From Serapanacheri to Panruti… — initial checks, 1.7 km away
- Laying of Underground Ofc Along Road Side From Serapanacheri to Panruti… — lapsed, 1.7 km away
- Proposed Expansion of Industrial Buildings by M/s. Doowon Automotive Systems… — initial checks, 2.3 km away
- Proposed 1X10 MW Coal based Co-Gen Thermal Power Plant — environmental approval granted, 2.3 km away
- Proposed 1X10 MW Coal based Co-Gen Thermal Power Plant — environmental approval granted, 2.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.