Project details
| Official title | Proposed Construction of High Rise Residential Building |
|---|---|
| Status | Environmental approval granted |
| Status since | 14 Sept 2025 |
| Application filed | 20 Jun 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Sunhera Realty Private Limited |
| Use | Residential |
| Units | 136 |
| Towers | 1 |
| Floors (tallest) | 25 |
| Basements | 2 |
| Height | 78 m |
| Parking spaces | 310 |
| Land area | 1.4 acres (0.6 ha) |
| Built-up area | 38,465 m² (4,14,033 sq ft) |
| Plot area | 5,672 m² (61,053 sq ft) |
| Project cost | ₹94.8 crore |
| Village / locality | Aminjikarai |
| Taluk / tehsil | Aminjikarai |
| District | Chennai |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-03536 |
What the filings say
The applicant, Sunhera Realty Private Limited, proposes to construct a high-rise residential building in Koyembedu, Aminjikarai. The project consists of a single block featuring two basement levels, a stilt or ground floor with a double-height reception, and 24 residential floors. The first floor is dedicated to community facilities including a gym, aerobics room, banquet hall, and indoor games area.
The residential portion comprises 136 dwelling units. This includes 90 units of three-bedroom apartments and 46 units of four-bedroom apartments. The building is designed to reach a maximum height of 77.95 metres, with a total built-up area of 38,464.86 square metres. The anticipated occupancy load is 916 persons, including 862 residents and 54 staff and visitors.
Key Figures
| Item | Detail |
|---|---|
| Total Built-up Area | 38,464.86 sq.m |
| Maximum Building Height | 77.95 m |
| Total Residential Units | 136 |
| Sewage Treatment Plant Capacity | 120 KLD |
| Car Parking Spaces Provided | 265 |
| Two-Wheeler Parking Spaces | 45 |
| Construction Duration | 42 months |
Layout and design
The project site occupies 0.567 hectares (1.40 acres). The ground coverage of the building is 1,180.87 square metres, representing 20.82% of the plot. A significant portion of the land is allocated to infrastructure and open spaces, including 1,835.45 square metres (32.36%) for roads and pavements, and 583.59 square metres (10.29%) for Open Space Reservation (OSR).
Parking facilities are distributed across the basement and surface areas, providing 265 car spaces and 45 two-wheeler spaces. Internal roads are planned with widths ranging from 3.0 to 6.0 metres to facilitate vehicle movement and fire tender access.
Land and surroundings
The site is located at Koyembedu in Aminjikarai Taluk, at an elevation of 13.0 metres above Mean Sea Level. The surrounding environment includes the Cooum River, located approximately 90 metres to the north. The AH 45 Chennai-Bangalore Highway is situated 10 metres from the site. Nearby landmarks include the Koyembedu Metro Railway Station (0.43 km west) and Guindy National Park (8.31 km south-east).
Water, power and access
Total water requirement is estimated at 120 kilolitres per day (KLD). The applicant intends to source 81 KLD of fresh water from the Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB). The remaining 39 KLD will be met through recycled water for flushing and gardening. A sewage treatment plant with a capacity of 120 KLD using Sequential Batch Reactor (SBR) technology will be installed to treat 94 KLD of generated sewage.
Power requirement is 1,500 KVA, to be sourced from the Tamil Nadu Power Distribution Corporation Limited (TNPDCL). Two diesel generator sets of 625 KVA each are proposed for emergency backup. Access to the site is provided via the Mount Poonamallee Road.
Environmental safeguards
The applicant proposes a greenbelt covering 850.84 square metres (15% of the plot), with plans to plant 82 trees of local species. For rainwater management, the project includes eight percolation pits and a 1,200 KL aquifer pond within the OSR area.
Solid waste management involves the segregation of 442 kg/day of domestic waste. An Organic Waste Convertor with a capacity of 25 kg per batch will treat 177 kg/day of biodegradable waste, producing manure for landscaping. Non-biodegradable waste (265 kg/day) will be handed over to authorized recyclers or the local municipal body. Energy conservation measures include LED lighting, solar water heaters, and a solar photovoltaic system expected to generate 63,786.29 kWh per annum. The project aims to achieve an IGBC Gold rating.
Timeline
The construction phase is expected to span 42 months. The proposed schedule indicates activities starting with ground levelling and foundation work, concluding with final testing and handing over by February 2029.
Sunhera Realty Construction of High Rise Residential Building site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
203 applications in Chennai since January 2022 are in the same category (Buildings & townships): 165 approved, 18 filed or under review, and 20 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1.4 acres, this one is smaller than 88% of them.
52 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Aminjikarai, Chennai, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Construction of High Rise Residential Building by Shriram Properties… — environmental approval granted, 300 m away
- Proposed Construction of High Rise Residential Building by Ramaniyam Real… — environmental approval granted, 500 m away
- Building project by M/S Appaswamy Real Estates LTD — lapsed, 1.3 km away
- Building project by M/S Appaswamy Real Estates LTD — environmental approval granted, 1.3 km away
- Amendment in Construction of Mixed-Use Development (Residential & Commercial)… — environmental approval granted, 1.7 km away
- Building project by M/s. Casagrand Millenia Private Limited — lapsed, 2.2 km away
- Building project by Casagrand Vistaaz Private Limited — lapsed, 2.3 km away
- Proposed Additional Construction of D. G. Vaishanav College at Survey Nos.… — more information requested, 2.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.