Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 20 Feb 2026 |
| Application filed | 5 Jan 2026 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Harris and Menuk Chemicals Private Limited |
| Land area | 2 acres (0.8 ha) |
| Project cost | ₹10.5 crore |
| Village / locality | Irrungattu Kottai |
| Taluk / tehsil | Sriperumbudur |
| District | Kanchipuram |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-04579 |
All filings for this project
This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 27 Feb 2026 | Environmental approval granted | 2 acres | ₹10.5 crore |
| Amendment filed 5 Jan 2026 (this page) | Environmental approval granted | 2 acres | ₹10.5 crore |
| New project filed 25 Sept 2024 | Environmental approval granted | 2 acres | ₹10.8 crore |
| Early planning filed 23 May 2024 | Cleared for impact study | 2 acres | ₹10.8 crore |
In context
25 applications in Kanchipuram since January 2022 are in the same category (Industry): 16 approved, 5 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 44 days from filing to approval. At 2 acres, this one is smaller than 88% of them.
17 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Irrungattu Kottai, Sriperumbudur, Kanchipuram, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Textile Processing Chemicals Manufacturing Facility — environmental approval granted, 0 m away
- Proposed Textile Processing Chemicals Manufacturing Facility — cleared for impact study, 0 m away
- Proposed Textile Processing Chemicals Manufacturing Facility — environmental approval granted, 0 m away
- Proposed Revamping and Modernization of HMIL Existing Manufacturing Facility… — environmental approval granted, 1 km away
- Proposed Revamping and Modernization of HMIL Existing Manufacturing Facility… — cleared for impact study, 1 km away
- Pharmaceutical Products Formulation unit by M/s. Esjay Pharma Pvt. Ltd — environmental approval granted, 1.7 km away
- Proposed Expansion and Modification of Student Housing Building by M/s. SPR… — under environmental review, 2.1 km away
- Laying of Aerial Ofc Along the Road Side Which Cross the Forest Areas of… — lapsed, 2.6 km away
All 4 Harris and Menuk Chemicals projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.