Puliyuran & Keelakandamankalam Village Rough Stone and Gravel Mining Project is an approved mining project in Keelakandamangalam, Tiruchuli, Virudhunagar, Tamil Nadu. The site covers 8.6 acres.
Who is building it?
The applicant is DILIP BUILDCON LIMITEd.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 24 Jul 2026), as of 27 Nov 2026.
Where is it?
In Keelakandamangalam, Tiruchuli, Virudhunagar, Tamil Nadu.
How big is it?
It has a stated cost of ₹75 lakh and a site of 8.6 acres.
When was it filed?
The application was filed on 29 Apr 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 24 Jul 2026 |
| Application filed | 29 Apr 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | DILIP BUILDCON LIMITEd |
| Land area | 8.6 acres (3.5 ha) |
| Project cost | ₹75 lakh |
| Village / locality | Keelakandamangalam |
| Taluk / tehsil | Tiruchuli |
| District | Virudhunagar |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-04695 |
In context
207 applications in Virudhunagar since January 2022 are in the same category (Mining): 152 approved, 34 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 8.6 acres, this one is larger than 71% of them.
No other mining lease on record is within 500 m of this site; 2 have applied within 5 km.
Where it is
Keelakandamangalam, Tiruchuli, Virudhunagar, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- VISHNU SURYA PROJECTS AND INFRA PRIVATE LIMITED Rough Stone and Gravel Quarry… — environmental approval granted, 800 m away
- VISHNU SURYA PROJECTS AND INFRA PRIVATE LIMITED Rough Stone and Gravel Quarry… — not approved, 800 m away
- VISHNU SURYA PROJECTS AND INFRA PRIVATE LIMITED Rough Stone and Gravel Quarry… — environmental approval granted, 800 m away
- VISHNU SURYA PROJECTS AND INFRA PRIVATE LIMITED Rough Stone and Gravel Quarry… — cleared for impact study, 800 m away
- Rough Stone and Gravel Quarry of Tmt.S.Meenakshi — environmental approval granted, 4.9 km away
- Rough Stone, Jelly and Gravel Quarry of Thiru.K.Balamurugan — environmental approval granted, 5.6 km away
- Rough Stone, Jelly and Gravel Quarry of Thiru.K.Balamurugan — environmental approval granted, 5.6 km away
- Roughstone and Gravel Quarry of Tmt.T.Muthulakshmi — environmental approval granted, 5.7 km away
All 45 Dilip Buildcon projects across India