Quick answers
What is this project?
Proposed Rough stone and Gravel Quarry of Tvl.Sai Blue Metals is a proposed mining project in Ammapatti, Vedasandur, Dindigul, Tamil Nadu. The site covers 2.4 acres.
Who is building it?
The applicant is Karthikeyan D.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Ammapatti, Vedasandur, Dindigul, Tamil Nadu.
How big is it?
It has a stated cost of ₹96 lakh and a site of 2.4 acres.
When was it filed?
The application was filed on 14 Jul 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 22 Sept 2026 |
| Application filed | 14 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Karthikeyan D |
| Land area | 2.4 acres (1 ha) |
| Project cost | ₹96 lakh |
| Village / locality | Ammapatti |
| Taluk / tehsil | Vedasandur |
| District | Dindigul |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-04823 |
In context
185 applications in Dindigul since January 2022 are in the same category (Mining): 121 approved, 36 filed or under review, and 27 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 2.4 acres, this one is smaller than 88% of them.
No other mining lease on record is within 500 m of this site; 7 have applied within 5 km.
Where it is
Ammapatti, Vedasandur, Dindigul, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Rough Stone and Gravel Quarry of Thiru.R.Vetrivel, — under wildlife review, 600 m away
- Proposed Rough stone and Gravel Quarry of Thiru.R.Vetrivel — lapsed, 600 m away
- Proposed Roughstone and Gravel Quarry of Thiru.N.Sathishkumar — environmental approval granted, 1000 m away
- Thiru. N. Sadhasivam Rough Stone Quarry Project — decision issued, 2 km away
- Thiru.N.Sadhasivam Rough stone quarry — environmental approval granted, 2 km away
- Proposed Rough stone Quarry of Thiru.S.Sakthivel — lapsed, 2.1 km away
- ERIODU MULTI COLOUR GRANITE QUARRY Belongs to C.RABEEK RAJA Extent: 1.24.5ha… — lapsed, 4.1 km away
- Rough Stone and Gravel Quarry of Thiru.R.Elango — under wildlife review, 9.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.