What is this project?
Proposed Expansion of Existing Sugar Unit From 2500 Tcd to 10000 Tcd is an approved industrial project in Nakatpura, Sitarganj, Udham Singh Nagar, Uttarakhand. The site covers 80 acres.
Who is building it?
The applicant is Jgn Sugar and Biofuels Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 16 Aug 2024), as of 27 Nov 2026.
Where is it?
In Nakatpura, Sitarganj, Udham Singh Nagar, Uttarakhand.
How big is it?
It has a stated cost of ₹8.5 crore and a site of 80 acres.
When was it filed?
The application was filed on 27 Apr 2024.
Project details
| Official title | Proposed Expansion of Existing Sugar Unit From 2500 Tcd to 10000 Tcd Along With Co Gen Power Plant of 22 MW and Establishment of Distillery Having Capacity 400 Kld (Based on Cane Juice Syrup / Molasses / Grains) Along With 9 MW Co Gen Power Within Sugar Industry Premises at Village - Sarkada & Nakatpura, Tehsil-Sitarganj, District – Udham Singh Nagar, Uttarakhand M/S Jgn Sugar & Biofuels PVT LTD, |
|---|---|
| Status | Environmental approval granted |
| Status since | 16 Aug 2024 |
| Application filed | 27 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Jgn Sugar and Biofuels Private Limited |
| Land area | 80 acres (32.4 ha) |
| Project cost | ₹8.5 crore |
| Village / locality | Nakatpura |
| Taluk / tehsil | Sitarganj |
| District | Udham Singh Nagar |
| State | Uttarakhand |
| Location from | Site boundary on record |
| Our reference | WID-UK-00368 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 27 Apr 2024 (this page) | Environmental approval granted | 80 acres | ₹8.5 crore |
| Early planning filed 16 Jun 2023 | Cleared for impact study | 80 acres | ₹8.5 crore |
In context
50 applications in Udham Singh Nagar since January 2022 are in the same category (Industry): 39 approved, 4 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 44 days from filing to approval. At 80 acres, this one is larger than 88% of them.
Where it is
Nakatpura, Sitarganj, Udham Singh Nagar, Uttarakhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of Existing Sugar Unit From 2500 Tcd to 10000 Tcd — cleared for impact study, 0 m away
- Turkatisor Sand Mining Project — environmental approval granted, 9.3 km away
- Common Solid Waste Management Facility at Sitarganj, Dist.-Udham Singh Nagar,… — under environmental review, 9.7 km away
- Common Solid Waste Management Facility at Sitarganj, Dist.-Udham Singh Nagar,… — returned to applicant, 9.7 km away
- Common Solid Waste Management Facility at Sitarganj, Dist.-Udham Singh Nagar,… — cleared for impact study, 9.7 km away
- OFC Bharat Net Project — more information requested, 11.1 km away
- Proposed Silt and Sand (RBM) Mining in Deoha River Khasra No. 510/9 Village-… — environmental approval granted, 13.2 km away
- Silt and Sand Mining in Deoha River Khasra No. 510/9, Village- Khamariya,… — withdrawn, 13.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.