Quick answers
What is this project?
Enhancement of MS Ingots/Billets production from 2,04,000 TPA to 3,74,000 TPA through installation of additional 24 T & 40 T IF is a proposed industrial project in Kundeshwara, Kashipur, Udham Singh Nagar, Uttarakhand. The site covers 14.8 acres.
Who is building it?
The applicant is Kashi Vishwanath Steels Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 15 Nov 2025), as of 27 Nov 2026.
Where is it?
In Kundeshwara, Kashipur, Udham Singh Nagar, Uttarakhand.
How big is it?
It has a stated cost of ₹199.2 crore and a site of 14.8 acres.
When was it filed?
The application was filed on 11 Nov 2025.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Enhancement of MS Ingots/Billets production from 2,04,000 TPA to 3,74,000 TPA through…
Project details
| Official title | Enhancement of MS Ingots/Billets production from 2,04,000 TPA to 3,74,000 TPA through installation of additional 24 T & 40 T IF, along with the installation of CCM & LRF of 25 T, Enhancement in production of Rolled Products from 2,00,000 TPA to 3,65,600 TPA along with existing cold drawing complex and metal recovery plant by M/s Kashi Vishwanath Steels Private Limited at Narain Nagar Industrial Estate, Bazpur Road, Kashipur, District Udham Singh Nagar, Uttarakhand |
|---|---|
| Status | Cleared for impact study |
| Status since | 15 Nov 2025 |
| Application filed | 11 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Kashi Vishwanath Steels Private Limited |
| Land area | 14.8 acres (6 ha) |
| Project cost | ₹199.2 crore |
| Village / locality | Kundeshwara |
| Taluk / tehsil | Kashipur |
| District | Udham Singh Nagar |
| State | Uttarakhand |
| Location from | Site boundary on record |
| Our reference | WID-UK-00606 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 23 Mar 2026 | Environmental approval granted | 14.8 acres | ₹199.2 crore |
| Early planning filed 11 Nov 2025 (this page) | Cleared for impact study | 14.8 acres | ₹199.2 crore |
In context
50 applications in Udham Singh Nagar since January 2022 are in the same category (Industry): 39 approved, 4 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 44 days from filing to approval. At 14.8 acres, this one is larger than 58% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kundeshwara, Kashipur, Udham Singh Nagar, Uttarakhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Enhancement of MS Ingots/Billets production from 2,04,000 TPA to 3,74,000 TPA… — environmental approval granted, 0 m away
- Regularization of existing Rolling mill plant for production of 237,600 TPA… — environmental approval granted, 250 m away
- Regularization of existing Rolling mill plant for production of 237,600 TPA… — cleared for impact study, 250 m away
- Transfer of Existing Environmental Clerance of Expansion of distillery unit by… — environmental approval granted, 1.9 km away
- Proposed change in raw material mix for the production of 600 KLD of Rectified… — initial checks, 2.1 km away
- "no Increase in Pollution Load" for Enhancement in Production Capacity of… — initial checks, 2.1 km away
- Surrender of EC for Proposed 120 KLD Grain Based Ethanol Plant with 3.0 MW… — withdrawn, 4.9 km away
- Proposed 300 KLPD Grain based Ethanol Plant by M/s DSK Foods Private Limited — environmental approval granted, 4.9 km away