Project details
| Official title | Greenfield Project of Grain Based Distillery Plant of 160 KLPD along with Co-generation Power Plant of 5.0 MW located at Khasra No.-317, 318, 319, 320 in Village-Malika and Khasra No.-111, 112 in Village-Karnapur, Tehsil-Powayan, Dist.-Shahjahanpur, Uttar Pradesh |
|---|---|
| Status | Environmental approval granted |
| Status since | 14 Mar 2023 |
| Application filed | 14 Mar 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Tqn Retails Private Limited |
| Land area | 16 acres (6.5 ha) |
| Project cost | ₹224.5 crore |
| Village / locality | Karnapur |
| Taluk / tehsil | Powayan |
| District | Shahjahanpur |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-00864 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 8 Jul 2026 | More information requested | 16 acres | ₹224.5 crore |
| New project filed 14 Mar 2023 (this page) | Environmental approval granted | 16 acres | ₹224.5 crore |
In context
29 applications in Shahjahanpur since January 2022 are in the same category (Industry): 25 approved, 4 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 16 acres, this one is smaller than 86% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Karnapur, Powayan, Shahjahanpur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Greenfield Project of Grain Based Distillery Plant of 160 KLPD — more information requested, 0 m away
- Rampur Khurd Soil Mining Project — environmental approval granted, 2.5 km away
- Haripur Soil Mining Project — environmental approval granted, 3.2 km away
- Daulatpur Soil Mining Project — environmental approval granted, 3.7 km away
- Lukmanpur Baheda Soil Mining Project — under environmental review, 6.4 km away
- Padariya Dalelpur Soil Mining Project — environmental approval granted, 6.6 km away
- Mainiya Mu. Mahua Soil Mining Project — environmental approval granted, 6.6 km away
- Mainiya Mu. Mahua Soil Mining Project — under environmental review, 6.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.