Quick answers
What is Industrial project by Wave Distilleries & Breweries Ltd.?
This proposed industrial project by Wave Distilleries & Breweries Ltd. is in Ahmadpura, Atrauli, Aligarh, Uttar Pradesh. The site covers 40.1 acres.
Who is building it?
The applicant is Wave Distilleries and Breweries Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 4 Feb 2025), as of 27 Nov 2026.
Where is it?
In Ahmadpura, Atrauli, Aligarh, Uttar Pradesh.
How big is it?
It has a stated cost of ₹110 crore and a site of 40.1 acres.
When was it filed?
The application was filed on 29 Jan 2025.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 4 Feb 2025 |
| Application filed | 29 Jan 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Wave Distilleries and Breweries Limited |
| Land area | 40.1 acres (16.2 ha) |
| Project cost | ₹110 crore |
| Village / locality | Ahmadpura |
| Taluk / tehsil | Atrauli |
| District | Aligarh |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-01545 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 16 Sept 2026 | Returned to applicant | 40.1 acres | ₹110 crore |
| Early planning filed 29 Jan 2025 (this page) | Cleared for impact study | 40.1 acres | ₹110 crore |
In context
9 applications in Aligarh since January 2022 are in the same category (Industry): 5 approved, 3 filed or under review, and 1 withdrawn, lapsed or rejected.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ahmadpura, Atrauli, Aligarh, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Industrial project by Wave Distilleries & Breweries Ltd. — returned to applicant, 0 m away
- Wave Distilleries and Breweries Ltd Grain Unit — initial checks, 50 m away
- Industrial project by Wave Distilleries and Breweries Limited — environmental approval granted, 50 m away
- Industrial project by Wave Distillery and Breweries Pvt. Ltd — lapsed, 50 m away
- Diversion of protected forest land for Four-lane widening and strengthening… — forest land use approved, 2 km away
- Expansion in Cement Production capacity of Existing Clinker Grinding Unit from… — environmental approval granted, 6.8 km away
- Expansion in Cement Production capacity of Existing Clinker Grinding Unit from… — more information requested, 6.8 km away
- Rasik Greens — environmental approval granted, 7.3 km away
More from Wave Distilleries and Breweries Limited in Aligarh
- Industrial project by Wave Distilleries and Breweries Limited — environmental approval granted
- Wave Distilleries and Breweries Ltd Grain Unit — initial checks
- Industrial project by Wave Distillery and Breweries Pvt. Ltd — lapsed
All 5 Wave Distilleries and projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.