Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 13 Mar 2025 |
| Application filed | 10 Oct 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Buildings & townships |
| Applicant | Diligent Builders Private Limited |
| Use | Residential |
| Towers | 2 |
| Floors (tallest) | 22 |
| Basements | 2 |
| Parking spaces | 502 |
| Land area | 2.5 acres (1 ha) |
| Built-up area | 58,383 m² (6,28,429 sq ft) |
| Plot area | 10,020 m² (1,07,854 sq ft) |
| Project cost | ₹323.7 crore |
| Village / locality | Bisrakh |
| Taluk / tehsil | Dadri |
| District | Gautam Buddha Nagar (Noida) |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-01867 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 10 Oct 2024 (this page) | Environmental approval granted | 2.5 acres | ₹323.7 crore |
| New project filed 9 Feb 2024 | Environmental approval granted | 2.5 acres | ₹162 crore |
In context
430 applications in Noida since January 2022 are in the same category (Buildings & townships): 306 approved, 90 filed or under review, and 34 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 2.5 acres, this one is smaller than 89% of them.
93 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bisrakh, Dadri, Noida, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Building project by M/S Diligent Builders Pvt. Ltd. — environmental approval granted, 0 m away
- Building project by Jmdr Infra Projects PVT. LTD. — environmental approval granted, 100 m away
- Proposed Expansion of Group Housing Project RG PLEIADES at plot no: GH-14B,… — environmental approval granted, 250 m away
- Proposed Expansion of Group Housing Project RG PLEIADES at plot no: GH-14B,… — cleared for impact study, 250 m away
- Proposed Group Housing Project "kvir Towers" on Plot No: Gh-14b, Sector -01,… — environmental approval granted, 250 m away
- Expansion of the Group Housing Project "Future Estate" at Plot No.: GH-16E,… — withdrawn, 650 m away
- Expansion of the Group Housing Project "Future Estate" at Plot No.: GH-16E,… — cleared for impact study, 650 m away
- Expansion of Proposed Group Housing Project "Future Estate" at Plot No GH-16… — under environmental review, 650 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.