Quick answers
What is this project?
Proposed Project of "Sand/Morrum Mining" on the Riverbed of Yamuna River at 117/1 (Khand No. 02), over an area of 10.0 Hectares is a lapsed mining project in Semra Shekhpur Diwara, Kalpi, Jalaun, Uttar Pradesh. The site covers 24.7 acres.
Who is building it?
The applicant is Urmila Singh.
Has it been approved?
No. The application was lapsed on 29 Sept 2026, so it is no longer under consideration.
Where is it?
In Semra Shekhpur Diwara, Kalpi, Jalaun, Uttar Pradesh.
How big is it?
It has a stated cost of ₹90 lakh and a site of 24.7 acres.
When was it filed?
The application was filed on 15 May 2025.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Proposed Project of "Sand/Morrum Mining" on the Riverbed of Yamuna River at 117/1 (Khand…
Project details
| Official title | Proposed Project of "Sand/Morrum Mining" on the Riverbed of Yamuna River at 117/1 (Khand No. 02), over an area of 10.0 Hectares situated in Village – Simrasheik Pur Dewra Tehsil- Kalpi, District Jalaun, Uttar Pradesh. |
|---|---|
| Status | Lapsed |
| Status since | 29 Sept 2026 |
| Application filed | 15 May 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Urmila Singh |
| Land area | 24.7 acres (10 ha) |
| Project cost | ₹90 lakh |
| Village / locality | Semra Shekhpur Diwara |
| Taluk / tehsil | Kalpi |
| District | Jalaun |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-03406 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 15 May 2025 (this page) | Lapsed | 24.7 acres | ₹90 lakh |
| Early planning filed 17 Oct 2024 | Cleared for impact study | 24.7 acres | ₹90 lakh |
In context
149 applications in Jalaun since January 2022 are in the same category (Mining): 100 approved, 40 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 24.7 acres, this one is smaller than 84% of them.
No other mining lease on record is within 500 m of this site; 2 have applied within 5 km.
Where it is
Semra Shekhpur Diwara, Kalpi, Jalaun, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Project of "Sand/Morrum Mining" on the Riverbed of Yamuna River at… — cleared for impact study, 0 m away
- Proposed Project of riverbed "Sand/Morrum Mining" on the riverbed of Yamuna… — environmental approval granted, 650 m away
- Proposed Project of riverbed "Sand/Morrum Mining" on the riverbed of Yamuna… — cleared for impact study, 650 m away
- Ordinary Soil Excavation — environmental approval granted, 2.3 km away
- Ordinary Sand Mining, Yamuna Riverbed, Gata No 2059, 2060 Khand-4, area 16.50… — cleared for impact study, 7.2 km away
- Ordinary Sand Mining, Yamuna Riverbed, Gata No 2059, 2060 Khand-4, area 16.50… — lapsed, 7.3 km away
- Ordinary Soil Mining Project at Gata No. 585, 771, Village - Gorakala, Tehsil… — environmental approval granted, 9.3 km away
- Sand/ Morrum Mining from Yamuna Riverbed — cleared for impact study, 12.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.