Project details
| Official title | Proposed Project of "Gitty/Boulder (Dolostone) Mining Project" located at Gata no- 4950, 4951, 4952, 4953, 4954 ख, 4955, 4956, 4958, 4960 (Lease Area 1.390 Ha) in Village- Billi Markundi, Tehsil Obra & District- Sonbhadra, Uttar Pradesh. Prop. Shri Manoj Singh. Area- 1.390 Ha |
|---|---|
| Status | Environmental approval granted |
| Status since | 8 Oct 2026 |
| Application filed | 25 May 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Manoj Singh |
| Land area | 3.4 acres (1.4 ha) |
| Project cost | ₹95 lakh |
| Village / locality | Kharaitiya |
| Taluk / tehsil | Robertsganj |
| District | Sonbhadra |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-04111 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 25 May 2026 (this page) | Environmental approval granted | 3.4 acres | ₹95 lakh |
| Early planning filed 14 Apr 2025 | Cleared for impact study | 3.4 acres | ₹95 lakh |
In context
209 applications in Sonbhadra since January 2022 are in the same category (Mining): 162 approved, 22 filed or under review, and 25 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 3.4 acres, this one is smaller than 62% of them.
7 other mining leases have applied within 500 m of this site; together with this one they cover 50.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 60 mining leases have applied within 5 km.
Where it is
Kharaitiya, Robertsganj, Sonbhadra, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Project of "Gitty/Boulder (Dolostone) Mining Project" located at Gata… — cleared for impact study, 0 m away
- Billi Markundi, Gitti, Boulder (Dolo Stone) Mining Project (Area 1.11 Ha.) — environmental approval granted, 200 m away
- Billi Markundi, Gitti, Boulder (Dolo Stone) Mining Project (Area 1.11 Ha.) — cleared for impact study, 200 m away
- Area- 1.530 Ha Gitti-Boulder (Dolostone) Mining Project Araji no. 5309क, 5311,… — environmental approval granted, 200 m away
- Area- 1.530 Ha Gitti-Boulder (Dolostone) Mining Project Araji no. 5309क, 5311,… — cleared for impact study, 200 m away
- Billi Markundi Khanda, Boulder (Dolostone) Mining Project (Area- 6.80 ha) — environmental approval granted, 300 m away
- Proposed Project of Gitti-Boulder (Dolostone) Mine at Arazi No 5414Ga, area… — lapsed, 300 m away
- Proposed Project of Gitti-Boulder (Dolostone) Mine at Arazi No 5414Ga, area… — cleared for impact study, 300 m away