One of 3 filings for this project. The project's main page, with every filing and where each stands: Expansion of Existing 300 KLPD B-Heavy Molasses/ Cane Juice/ Grain Based Distillery to…
Project details
| Official title | Expansion of Existing 300 KLPD B-Heavy Molasses/ Cane Juice/ Grain Based Distillery to 600 KLPD Cane Juice/ Grain Based Distillery along with 6.0 MW Co-generation Power Plant at Village Rani Nagal & Sardar Nagar, Tehsil & District Moradabad, Uttar Pradesh |
|---|---|
| Status | Returned to applicant |
| Status since | 31 Aug 2026 |
| Application filed | 17 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Karimganj Biofuels Private Limited |
| Land area | 10.9 acres (4.4 ha) |
| Project cost | ₹124 crore |
| Village / locality | Rani Nagla |
| Taluk / tehsil | Moradabad |
| District | Moradabad |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-04486 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 30 Sept 2026 | Environmental approval granted | 10.9 acres | ₹124 crore |
| Expansion filed 17 Jul 2026 (this page) | Returned to applicant | 10.9 acres | ₹124 crore |
| Early planning filed 13 Mar 2025 | Cleared for impact study | 10.9 acres | ₹124 crore |
In context
20 applications in Moradabad since January 2022 are in the same category (Industry): 13 approved, 5 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 36 days from filing to approval. At 10.9 acres, this one is smaller than 94% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Rani Nagla, Moradabad, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Existing 300 KLPD B-Heavy Molasses/ Cane Juice/ Grain Based… — environmental approval granted, 0 m away
- Expansion of Existing 300 KLPD B-Heavy Molasses/ Cane Juice/ Grain Based… — cleared for impact study, 0 m away
- Industrial project by Rana Sugars Limited — initial checks, 100 m away
- Industrial project by Rana Sugars Limited — initial checks, 100 m away
- Proposed "Ordinary Soil Excavation" Project at Gata No.–6 — environmental approval granted, 250 m away
- Area: 0.905 Ha. "Ordinary Soil Excavation" Project at Gata No.– 461 — environmental approval granted, 900 m away
- Ordinary Soil — environmental approval granted, 1.4 km away
- Proposed "Ordinary Soil Mining Project" at Gata 482 & 530 by Shri Riyazul S/o… — under environmental review, 1.6 km away
All 3 Karimganj Biofuels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.