Quick answers
What is this project?
Proposed Protected Forest Land to be Diverted for "Construction of Two-Lane Bypass to Mungrabadshapur Town Starting from Near Kodahu at Km 47/225 of NH-319D and Ending Near Nauwadandi at Km 218/880 of NH-31 is an approved road project in Goraiya Dih, Machhlishahr, Jaunpur, Uttar Pradesh. The site covers 31.3 acres.
Who is building it?
The applicant is National Highway Authority of India.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 2 Dec 2025), as of 27 Nov 2026.
Where is it?
In Goraiya Dih, Machhlishahr, Jaunpur, Uttar Pradesh.
How big is it?
It has a stated cost of ₹197.6 crore; a site of 31.3 acres and 3,780 m² of forest land.
When was it filed?
The application was filed on 20 Feb 2025.
Project details
| Official title | Proposed Protected Forest Land to be Diverted for "Construction of Two-Lane Bypass to Mungrabadshapur Town Starting from Near Kodahu at Km 47/225 of NH-319D and Ending Near Nauwadandi at Km 218/880 of NH-31 in District: Jaunpur (U.P) |
|---|---|
| Status | Forest land use approved |
| Status since | 2 Dec 2025 |
| Application filed | 20 Feb 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | National Highway Authority of India |
| Land area | 31.3 acres (12.7 ha) |
| Forest land | 3,780 m² |
| Project cost | ₹197.6 crore |
| Village / locality | Goraiya Dih |
| Taluk / tehsil | Machhlishahr |
| District | Jaunpur |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-06080 |
In context
14 applications in Jaunpur since January 2022 are in the same category (Roads & highways): 7 approved, 1 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 13 months from filing to approval. At 31.3 acres, this one is larger than 57% of them.
Where it is
Goraiya Dih, Machhlishahr, Jaunpur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 40 MW Captive Power Plant - Jaunpur — lapsed, 5.1 km away
- Common Bio Medical Waste Treatment Facility (CBWTF) M/s R.S. BMW Services Plot… — cleared for impact study, 5.5 km away
- Common Bio Medical Waste Treatment Facility (CBWTF) M/s R.S. BMW Services Plot… — environmental approval granted, 5.5 km away
- Waste management project by Prayagraj Mediserve Private Limited — lapsed, 6.5 km away
- Proposed Protected Forest Land to be Diverted for Entry/Exit Approach to IOCL… — forest land use approved, 7.8 km away
- Proposed Forest Land to be Diverted for Entry/Exit Approach to BPCL Retail… — lapsed, 11.4 km away
- Proposed Protected Forest Land to be Diverted for Entry/Exit Approach to IOCL… — forest land use approved, 12.8 km away
- Proposed protected forest land to be diverted for Entry/Exit approach to BPCL… — forest land use approved, 17.5 km away
All 548 National Highways Authority of India (NHAI) projects across India