Project details
| Official title | Manufacturing Speciality Chemicals and Disinfectant Chemicals in Existing Unit by Salts and Chemicals PVT. Limited at Village & Po - Sugandha, Dist. - Hooghly, West Bengal |
|---|---|
| Status | Environmental approval granted |
| Status since | 17 Nov 2022 |
| Application filed | 17 Nov 2022 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | M/S Salts and Chemicals Private Limited. |
| Land area | 1.2 acres (0.5 ha) |
| Project cost | ₹22 lakh |
| Village / locality | Sugandha |
| Taluk / tehsil | Polba - Dadpur |
| District | Hooghly |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00055 |
In context
20 applications in Hooghly since January 2022 are in the same category (Industry): 16 approved, 4 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 1.2 acres, this one is smaller than 75% of them.
Where it is
Sugandha, Polba - Dadpur, Hooghly, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Modification & Expansion of Residential Complex by Girdhar Tracom Pvt. Ltd.… — environmental approval granted, 6.7 km away
- Warehouse Building Project by Nahar Industrial Enterprises Ltd. — lapsed, 8 km away
- Coal Tar Distillation Project to Manufacture 18,144 MTPA Coal tar Pitch,… — environmental approval granted, 11.3 km away
- Coal Tar Distillation Project to Manufacture 18,144 MTPA Coal tar Pitch,… — cleared for impact study, 11.3 km away
- Environmental Clearance (Ec) for the Ongoing Project and Its Small Expansion… — environmental approval granted, 11.5 km away
- Proposed Increase in the Paper Production Capacity From 60,000 Tpa to 84,000… — returned to applicant, 12.9 km away
- Environmental Impact Assessment for Proposed Increase in the Paper Production… — environmental approval granted, 13.1 km away
- Modification of Existing Carbon Black Manufacturing Process for Higher… — initial checks, 13.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.