What is Developing? Open the mapMap

LapsedIndustry · Paschim Bardhaman, West Bengal

Proposed expansion of existing Steel Plant by installation of Sponge Iron Plant with 2x200 TPD DRI Kilns, 4x15 T Induction Furnaces, 400 TPD Rolling Mill & 8 MW capacity WHRB based Captive Power Plant.

Proposed expansion of existing Steel Plant by installation of Sponge Iron Plant with 2x200 TPD DRI Kilns, 4x15 T Induction Furnaces, 400 TPD Rolling Mill & 8 MW capacity WHRB based Captive Power Plant is a lapsed industrial project in Ikra, Jamuria, Paschim Bardhaman, West Bengal. The site covers 19.3 acres. Its stated project cost is ₹150 crore. As of 27 Nov 2026, its status is “Lapsed” (since 25 Jan 2025).

See it on the live map All projects in Paschim Bardhaman

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

One of 3 filings for this project. The project's main page, with every filing and where each stands: Proposed expansion of existing Steel Plant by installation of Sponge Iron Plant with…

Project details

StatusLapsed
Status since25 Jan 2025
Application filed1 Aug 2023
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantCalstar Sponge Limited
Land area19.3 acres (7.8 ha)
Project cost₹150 crore
Village / localityIkra
Taluk / tehsilJamuria
DistrictPaschim Bardhaman
StateWest Bengal
Location fromSite boundary on record
Our referenceWID-WB-00283

All filings for this project

This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 5 Apr 2024Under environmental review19.3 acres₹150 crore
Expansion filed 5 Sept 2023Returned to applicant19.3 acres₹150 crore
Early planning filed 1 Aug 2023 (this page)Lapsed19.3 acres₹150 crore

In context

169 applications in Paschim Bardhaman since January 2022 are in the same category (Industry): 81 approved, 49 filed or under review, and 39 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 19.3 acres, this one is smaller than 70% of them.

64 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Ikra, Jamuria, Paschim Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 3 Calstar Sponge projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.