Project details
| Official title | Proposed installation of the Ferro Alloy Plant through setting up of 2x9 MVA Submerged Arc Furnaces for production of Ferro Manganese (18000 TPA) and Silico Manganese (12000 TPA) & Sinter Plant (9000TPA) by M/s. Shyam Business Solution Pvt. Ltd. at Raturia, Angadpur Industrial Area, Tehsil – Durgapur Dist. – Paschim Bardhaman, West Bengal |
|---|---|
| Status | Environmental approval granted |
| Status since | 11 Feb 2025 |
| Application filed | 7 Oct 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Shyam Business Solution PVT LTD |
| Land area | 5.6 acres (2.3 ha) |
| Project cost | ₹45 crore |
| Village / locality | Raturia |
| Taluk / tehsil | Faridpur Durgapur |
| District | Paschim Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00434 |
In context
169 applications in Paschim Bardhaman since January 2022 are in the same category (Industry): 81 approved, 49 filed or under review, and 39 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 5.6 acres, this one is smaller than 92% of them.
27 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Raturia, Faridpur Durgapur, Paschim Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 'No Increase in Pollution Load' for Proposed Installation of additional 02… — initial checks, 300 m away
- Proposed expansion of Sponge Iron Unit by installation of new Steel Rolling… — lapsed, 300 m away
- Proposed Steel Rolling Mill at Raturia Industrial Area, Angadpur, PO:… — returned to applicant, 300 m away
- Upgradation of Existing Production Units and Additional Facilities to Produce… — lapsed, 550 m away
- Capacity enhancement of existing Mini Blast Furnace (MBF), Sinter Plant and… — initial checks, 550 m away
- Proposed Expansion of the Existing Steel Plant by Installation of 4x30 T… — environmental approval granted, 750 m away
- Request for change of Company name in TOR for Proposed expansion of the… — cleared for impact study, 750 m away
- Modification/Addition of Product Mix Without Change in Production Capacity of… — initial checks, 1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.