Regularization of Environmental Clearance for Expansion of Existing Rolling Mill Producing Angles & Channels and Pickling followed by Galvanizing of Rolled items, including Establishing a New Project of Manufacturing Transmission tower and High Mast Pole using the same Rolled and Galvanized products of M/s, SKIPPER LIMITED

Regularization of Environmental Clearance for Expansion of Existing Rolling Mill Producing Angles & Channels and Pickling followed by Galvanizing of Rolled items, including Establishing a New Project of Manufacturing Transmission tower and High Mast Pole using the same Rolled and Galvanized products of M/s, SKIPPER LIMITED is a rejected industrial project in Kashyappur, Uluberia - I, Howrah, West Bengal. The site covers 61.6 acres. Its stated project cost is ₹6.1 crore. As of 27 Nov 2026, its status is “Not approved” (since 25 Jul 2025).

See it on the live map All projects in Howrah

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Regularization of Environmental Clearance for Expansion of Existing Rolling Mill Producing Angles & Channels and Pickling followed by Galvanizing of Rolled items, including Establishing a New Project of Manufacturing Transmission tower and High Mast Pole using the same Rolled and Galvanized products of M/s, SKIPPER LIMITED is a rejected industrial project in Kashyappur, Uluberia - I, Howrah, West Bengal. The site covers 61.6 acres.

Who is building it?

The applicant is Yash Jain.

Has it been approved?

No. The application was rejected on 25 Jul 2025.

Where is it?

In Kashyappur, Uluberia - I, Howrah, West Bengal.

How big is it?

It has a stated cost of ₹6.1 crore and a site of 61.6 acres.

When was it filed?

The application was filed on 1 Jul 2025.

Project details

StatusNot approved
Status since25 Jul 2025
Application filed1 Jul 2025
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantYash Jain
Land area61.6 acres (24.9 ha)
Project cost₹6.1 crore
Village / localityKashyappur
Taluk / tehsilUluberia - I
DistrictHowrah
StateWest Bengal
Location fromSite boundary on record
Our referenceWID-WB-01246

In context

35 applications in Howrah since January 2022 are in the same category (Industry): 25 approved, 5 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 61.6 acres, this one is larger than 85% of them.

6 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kashyappur, Uluberia - I, Howrah, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.