Project details
| Status | More information requested |
|---|---|
| Status since | 26 Nov 2026 |
| Application filed | 29 May 2026 |
| Approval sought | Forest land use |
| Application type | Ownership transfer |
| Sector | Pipelines |
| Applicant | Essar Oil and Gas Limited |
| Land area | 31 acres (12.6 ha) |
| Forest land | 33.5 acres (13.5 ha) |
| Project cost | ₹324 crore |
| Village / locality | Akandara |
| Taluk / tehsil | Kanksa |
| District | Paschim Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-02281 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 8 Jun 2026 | Lapsed | 31 acres | ₹324 crore |
| Ownership transfer filed 29 May 2026 (this page) | More information requested | 31 acres | ₹324 crore |
In context
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Akandara, Kanksa, Paschim Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Pipeline project by Essar Oil and Gas Limited — lapsed, 0 m away
- Pipeline project by Essar Oil and Gas Limited — lapsed, 0 m away
- CBM Raniganj FDP-4 — lapsed, 900 m away
- CBM Raniganj FDP-4 — more information requested, 900 m away
- Development & Production Wells alongwith Surface Facilities, Phase III of CBM… — lapsed, 2.2 km away
- Application for diversion of 0.6151 Ha of forest land for the expansion of an… — lapsed, 4.8 km away
- Exploration and Development Drilling alongwith Surface Facililities, Phase IV… — returned to applicant, 6.3 km away
- Exploration and Development Drilling alongwith Surface Facililities, Phase IV… — cleared for impact study, 6.3 km away
More from Essar Oil and Gas Limited in Paschim Bardhaman
- Pipeline project by Essar Oil and Gas Limited — lapsed
- CBM Raniganj FDP-4 — lapsed
- CBM Raniganj FDP-4 — more information requested
- Exploration and Development Drilling alongwith Surface Facililities, Phase IV… — cleared for impact study
All 6 Essar Oil and Gas projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.