| Proposed Pipeline for Transportation of Natural Gas in Gujarat State From Anjar to… Khareda, Patan, Gujarat | Pipelines | 6.2 acres | Under environmental review | 19 Nov 2026 |
| Mundra – Mandvi Gas Pipeline Project Kandagara Mota, Kachchh, Gujarat | Pipelines | 9.4 acres | Initial checks | 29 Oct 2026 |
| ESSAR Future Energy Limited Connectivity Kajurda, Devbhumi Dwarka, Gujarat | Pipelines | 0.6 acres | Under forest review | 14 Oct 2026 |
| Anjar – Palanpur Pipeline Project (From Anjar (Ratatalav) to Palanpur (Chatodar)… Amblun, Banas Kantha, Gujarat | Pipelines | 1,367.2 acres | More information requested | 31 Jul 2026 |
| Diversion of wildlife area for the purpose of laying "proposed 30"∅ Gas Pipeline from… Arjansar, Patan, Gujarat | Buildings & townships | 702 acres | Under wildlife review | 29 Oct 2025 |
Where Gspl Transmission is building
Questions people ask
How many projects has Gspl Transmission filed?
5 since January 2022, of which 0 are approved and 5 are awaiting a decision.
Where are Gspl Transmission's projects?
Mostly in Patan, Gujarat (2), Kachchh, Gujarat (1), Devbhumi Dwarka, Gujarat (1) and Banas Kantha, Gujarat (1).
What did Gspl Transmission file most recently?
Proposed Pipeline for Transportation of Natural Gas in Gujarat State From Anjar to Palanpur in Khareda, Patan, filed on 19 Nov 2026. Status: Under environmental review.
About this information
Compiled from publicly available approval records, grouped by the applicant's registered name. What is Developing? is not affiliated with Gspl Transmission; the badge is generated from its name. Group companies that file under different names may appear on separate pages. Statuses can change between our updates; check with the authority before making decisions. Spotted a mistake? Tell us.