RCCPL upcoming projects in Satna

RCCPL Private Limited has filed 7 projects in Satna for environmental, forest, wildlife or coastal approval since January 2022: 3 approved and 4 awaiting a decision. They are in Sannai, Sarhera, Karhi Pawai and Kherwa Kalan, covering 6,891.9 acres with a stated cost of ₹10,161.9 crore. The latest was filed on 27 Oct 2026.

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

7projects filed
4awaiting approval
1districts

All 7 projects, newest first

ProjectTypeSizeStatusFiled
Increase in Clinker Production From 4 Million Tpa to 8.5 Million Tpa Through Addition of…
Sannai, Satna, Madhya Pradesh
Industry443.8 acresMore information requested27 Oct 2026
Forest Clearance in Favour of M/S Rccpl PVT. LTD. for Diverting 24.24 Hect. (17.13 Hect.…
Sarhera, Satna, Madhya Pradesh
Roads & highways4,086.9 acresUnder forest review2 Sept 2026
Itoura Limestone Mining with 0.8 MTPA capacity at villages Itoura, Bachwai, Karhi Pawai,…
Karhi Pawai, Satna, Madhya Pradesh
Mining1,688 acresEnvironmental approval granted3 Aug 2026
Change in Land Use in Favour of M/S Rccpl PVT. LTD. for Second Conveyor Belt (Olbc-2) in…
Sannai, Satna, Madhya Pradesh
Mining33.6 acresUnder forest review29 Apr 2026
Increase in Clinker Production From 4 Million Tpa to 8.5 Million Tpa Through Addition of…
Kherwa Kalan, Satna, Madhya Pradesh
Industry443.8 acresUnder environmental review13 Mar 2026
Limestone Mine 889.76 Hectare Village Jamuani Khurd, Chari, Durjanpur, and Padrehi
Ghorwai, Satna, Madhya Pradesh
Mining97.9 acresEnvironmental approval granted10 Apr 2025
Limestone Mine 889.76 Hectare Village Jamuani Khurd, Chari, Durjanpur, and Padrehi
Bhoteura, Satna, Madhya Pradesh
Mining97.9 acresEnvironmental approval granted1 Dec 2023

RCCPL projects by city

All 11 RCCPL projects across India

Where RCCPL is building in Satna

Questions people ask

How many projects has RCCPL filed in Satna?

7 in Satna since January 2022, of which 3 are approved and 4 are awaiting a decision.

Where are RCCPL's projects in Satna?

Mostly in Satna, Madhya Pradesh (7).

What did RCCPL file most recently in Satna?

Increase in Clinker Production From 4 Million Tpa to 8.5 Million Tpa Through Addition of New Unit (Line-Ii) of 4.5 Million Tpa of Clinker and Power Generation Through Whrb From 12.25 MW to 32.25 MW in Sannai, Satna, filed on 27 Oct 2026. Status: More information requested.

About this information

Compiled from publicly available approval records, grouped by the applicant's registered name. What is Developing? is not affiliated with RCCPL; the badge is generated from its name. Group companies that file under different names may appear on separate pages. Statuses can change between our updates; check with the authority before making decisions. Spotted a mistake? Tell us.