Feature · Surguja and Surajpur, Chhattisgarh

Adani Power Proposes a 4,800-MW Thermal Plant in Surguja and Surajpur, Chhattisgarh

Adani Power Limited has proposed a 4,800-megawatt coal-based thermal power plant across Surguja and Surajpur districts in Chhattisgarh, requiring an investment of ₹56,030 crore.

Where it stands: Proposed 4800 (6x800) MW Coal Based Ultra Super-Critical Thermal Power Project at Salka,… — “Under environmental review” since 20 Nov 2026. 2 related filings are listed below. Status data as of 27 Nov 2026, 6:36 am IST.

Adani Power Limited proposes to build a 4,800-megawatt (MW) coal-based ultra super-critical thermal power project in Chhattisgarh. The facility is planned across the villages of Salka, Kathmunda, Narayanpur, Mudgaon, and adjacent areas in the Premnagar and Udaypur tehsils of Surguja and Surajpur districts. The project has a proposed capacity of 6x800 MW and an estimated cost of ₹56,030 crore. It is currently under environmental and forest review.

ItemDetail
ApplicantAdani Power Limited
Capacity4,800 MW (6x800 MW)
Estimated cost₹56,030 crore
Total land673.5 hectares (1,664.2 acres)
Forest land260.746 hectares (644.3 acres)

What is planned

The applicant plans to construct a coal-based ultra super-critical thermal power plant comprising six units of 800 MW each. According to the layout plans filed with the application, the complex will include a main plant area, an ash dyke, a raw water reservoir, and check dams.

Where it is and the land

The project site spans multiple villages including Salka, Kathmunda, Narayanpur, and Mudgaon. The total land required for the project is 673.5 hectares (1,664.2 acres). According to the most recent forest clearance filing from November 2026, this includes 260.746 hectares (644.3 acres) of forest land. An earlier environmental filing from September 2026 did not specify the forest land area. The applicant's cost-benefit analysis document states that no human resettlement is involved in the project.

Cost, jobs and schedule

The estimated construction cost of the project is ₹56,030 crore. According to the applicant's cost-benefit analysis, the construction phase is scheduled to last 76 months. During this period, the project is expected to generate 450 permanent jobs and 12,500 temporary jobs. Once operational, the plant has a projected lifespan of 25 years and will provide 550 direct and 3,500 indirect jobs. The applicant estimates the economic benefit from employment during the construction and operation phases to be over ₹5,03,357 lakh.

Water, power and connectivity

Layout maps show the Atem River flowing near the project boundary, with check dams proposed along its course. The site is located approximately 4.8 kilometres from National Highway 130 near Gumga village. For rail connectivity, Tarkeshwarpur Station is about 5.3 kilometres away, and Shivnagar Station is 10.2 kilometres away. The Adani Parsa Coal Mine in Kete, Sarguja, is located 12 kilometres from the site.

Environmental concerns and safeguards

The applicant's baseline study summary outlines plans to monitor ambient air quality for pollutants such as particulate matter (PM10 and PM2.5), sulphur dioxide, nitrogen dioxide, and carbon monoxide at 12 locations. Water quality will be tested from surface sources like rivers and ponds, as well as groundwater from handpumps and tube wells. The study will also include an inventory of terrestrial and aquatic flora and fauna within a 10-kilometre radius, and noise level measurements over 24-hour periods.

The cost-benefit analysis accounts for ecosystem service losses and habitat fragmentation due to the diversion of forest land. The applicant has proposed compensatory afforestation and soil and moisture conservation measures to mitigate these impacts, estimating the cost for these conservation efforts at ₹2,610 lakh.

Approvals so far

The project is currently under environmental review, with an application filed in September 2026. It is also under forest review following a separate application submitted in November 2026.

Filings for this project

FilingApproval soughtStatusFiledStatus since
Proposed 4800 (6x800) MW Coal Based Ultra Super-Critical Thermal Power Project…
Early planning · Kathmunda, Udaypur, Surguja
Environmental approvalUnder environmental review17 Sept 202620 Nov 2026
Proposed 4800 (6x800) MW Coal Based Ultra Super-Critical Thermal Power Project…
New project · Kathmunda, Udaypur, Surguja
Forest land useMore information requested6 Nov 202617 Nov 2026

Statuses update automatically twice a day.

About this page

Written and maintained by Akshay Syam. Filing statuses are compiled from publicly available approval records and refresh twice a day; a filing is not an approval. About our methods · Spotted a mistake? Tell us.