Projects by type
| Type | Projects |
|---|---|
| Buildings & townships | 20 |
| Other | 9 |
| Public facilities | 8 |
| Water & irrigation | 4 |
| Power | 3 |
| Roads & highways | 2 |
| Fuel stations | 1 |
| Telecom | 1 |
| Airports | 1 |
Where they are in the approval process
| Status | Projects |
|---|---|
| Filed or under review | 13 |
| Approved | 2 |
| Withdrawn or lapsed | 34 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| 400 kV D/C Jangi-Shongtong-Wangtoo (Quad) Transmission Line Agade (31/ 7), Nichar | Power | 538.3 acres | More information requested | 22 Oct 2026 |
| Shongtong Karcham HEP 450 MW Gonang (15/3), Kalpa | Water & irrigation | 6.1 acres | Under environmental review | 1 Sept 2026 |
| Horticulture Office-cum-complex, Vermicompost Demo Unit, Field Hostel and demo Orchard… Reckong Peo (18), Kalpa | Buildings & townships | 0.7 acres | Lapsed | 25 Aug 2026 |
| Construction of Petrol Pump at Chango, Distt. Kinnaur, HP Dhar Kawe(30), Hangrang | Fuel stations | 2.6 acres | Lapsed | 12 Aug 2026 |
| For construction of infrastructure at MM Ridge ,Vill -Namgia,Teh Pooh,District… D.P.F.C-199 (29), Poo | Roads & highways | 548.4 acres | Lapsed | 2 Aug 2026 |
| Melan Small Hydro Project (9.6 MW) D.P.F.Bargde C-252 (105), Nichar | Water & irrigation | 9 acres | Lapsed | 21 Jun 2026 |
| Indo-Tibetan Border Police (ITBP) Forward Post at Nithal Thach, District Kinnaur,… Dhar Nithal (73), Sangla | Public facilities | 4 acres | Under wildlife review | 13 Apr 2026 |
| Shifting of Ammunition Point Powari to Shaling Dhar Baltha Chang Dhar (78), Nichar | Other | 230.7 acres | Under wildlife review | 10 Jan 2026 |
| 400 KV D/C Transmission Line (4.897 Km) From 450 MW Shongtong Hep to the Tower No-04 of… Dakhaye (30/4), Kalpa | Power | 55.7 acres | More information requested | 7 Oct 2025 |
| Diversion of 00-27-50 Hectare forest land for development of Military Infrastructure at… Dhar Mujlang (67), Sangla | Other | 0.7 acres | Under wildlife review | 18 Dec 2024 |
| Diversion of 1 Hac. of Forest Land in Favour of Hangrang Rinchen Buddhist Cultural… Dhar Chang Chimo (10), Poo | Public facilities | 2.5 acres | Lapsed | 4 Dec 2024 |
| Construction of Forward Post Nithal Thach Dhar Nithal (73), Sangla | Other | 10.8 acres | More information requested | 26 Oct 2024 |
| Diversion of 00-27-50 Hectare forest land for development of Military Infrastructure at… Dhar Mujlang (67), Sangla | Other | 0.7 acres | More information requested | 3 Sept 2024 |
| 20MW Raura- II Hep Meeru Khas (104/1), Nichar | Water & irrigation | 8 acres | More information requested | 10 Jun 2024 |
| Project by M/s Him Fresh Product Pvt. Ltd. Paringkhor . Paring Khor (31/1), Nichar | Other | 1.8 acres | Lapsed | 26 Mar 2024 |
| Construction of Forward Post Nithal Thach Dhar Nithal (73), Sangla | Other | 4 acres | More information requested | 18 Jan 2024 |
| Diversion of Forest Land for Establishment of Border Out Post of Indo-Tibetan Border… Dhar Parmati (55), Morang | Public facilities | 0.3 acres | Lapsed | 19 Aug 2023 |
| Diversion of Forest Land for Establishment of Border Out Post of Indo-Tibetan Border… Dhar Doge (79), Morang | Public facilities | 3.8 acres | Lapsed | 19 Aug 2023 |
| Diversion of Forest Land for Establishment of Border Out Post of Indo-Tibetan Border… Dhar Lung Kurkur (83), Morang | Public facilities | 3.7 acres | Lapsed | 18 Aug 2023 |
| Diversion of Forest Land for Establishment of Border Out Post of Indo-Tibetan Border… D.P.F.C-199 (29), Poo | Public facilities | 4.3 acres | Lapsed | 18 Aug 2023 |
| Diversion of Forest Land for Establishment of Border Out Post of Indo-Tibetan Border… Wevgya (59/3), Morang | Public facilities | 4 acres | Lapsed | 18 Aug 2023 |
| Diversion of Forest Land for Establishment of Border Out Post of Indo-Tibetan Border… Gigu Lang (59/2), Morang | Public facilities | 2 acres | Lapsed | 17 Aug 2023 |
| Strategic Border Intelligence Out Post Shurting Dhar Gramangbal (68), Morang | Telecom | 2.1 acres | Lapsed | 28 Jul 2023 |
| Diversion of 25 Hectare Forest Land for Establishment of Military Infrastructure in… Dhar Dumti (72), Sangla | Other | 3,527.2 acres | Application filed | 27 Jul 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Up Mohal Shyaso (17), Poo | Buildings & townships | 0 acres | Lapsed | 4 Jun 2023 |
| Construction of Nagasti Helipad Chhitkul (63), Sangla | Airports | 0.2 acres | Under wildlife review | 23 May 2023 |
| C/O of Stone Crusher for execution of Border roads under BRO by LSR LOGISTICS (P) LTD Dhar Liyosu (34), Hangrang | Roads & highways | 1.9 acres | Lapsed | 5 Apr 2023 |
| Diversion of 25 Hectare Forest Land for Establishment of Military Infrastructure in… Dhar Dumti (72), Sangla | Other | 24,247.5 acres | Application filed | 12 Mar 2023 |
| Electric Vehicle Charging Station at M/s Donbusche HP center Tapri Tapri (91/3), Nichar | Power | 0 acres | Forest land use approved | 16 Feb 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Thang Karma (29/4), Hangrang | Buildings & townships | 0 acres | Lapsed | 3 Feb 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Lapo (16/2), Morang | Buildings & townships | 0 acres | Lapsed | 3 Feb 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Chakra (16/5), Morang | Buildings & townships | 0 acres | Lapsed | 3 Feb 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Dhar Wadang (26), Sangla | Buildings & townships | 0 acres | Lapsed | 24 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Yuldang (102/2), Nichar | Buildings & townships | 0 acres | Lapsed | 23 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Dhar Tipung (77), Morang | Buildings & townships | 0 acres | Lapsed | 23 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility D.P.F.C-152 (B) (31), Sangla | Buildings & townships | 0 acres | Lapsed | 21 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Ramni Khas (75/1), Nichar | Buildings & townships | 0 acres | Lapsed | 18 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Punang Kanda (90/2), Nichar | Buildings & townships | 0 acres | Lapsed | 17 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Raag Panung (91/4), Nichar | Buildings & townships | 0 acres | Lapsed | 16 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Up Mohal Chelit Kanda (15/3), Poo | Buildings & townships | 0 acres | Lapsed | 16 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Bara Kamba (7/3), Nichar | Buildings & townships | 0 acres | Lapsed | 13 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Goli (17/3), Kalpa | Buildings & townships | 0 acres | Lapsed | 13 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Kibar (47), Morang | Buildings & townships | 0 acres | Lapsed | 13 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Rango (31/4), Nichar | Buildings & townships | 0 acres | Lapsed | 13 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Nang Kashang (6/5), Kalpa | Buildings & townships | 0 acres | Lapsed | 13 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Kashag Gramag (6/4), Kalpa | Buildings & townships | 0 acres | Lapsed | 13 Jan 2023 |
| Mobile Tower to provide Telecommunication Line/Facility Galding (1/1), Nichar | Buildings & townships | 0 acres | Lapsed | 13 Jan 2023 |
| Pooh Signal Tekri D.P.F.C-199 (29), Poo | Other | 1.4 acres | Lapsed | 8 Jan 2023 |
| C/O HUBRA-II, 4.8 MW, HEP at Kinnaur D.P.F Hurua-C-156 (41), Sangla | Water & irrigation | 33,606.3 acres | Forest land use approved | 2 Nov 2022 |
Questions people ask
How many projects are planned in Kinnaur?
49 projects in Kinnaur have applied for approval since January 2022. 15 of them are active (not withdrawn, lapsed or rejected) and 13 are still awaiting a decision.
What was approved most recently in Kinnaur?
C/O HUBRA-II, 4.8 MW, HEP at Kinnaur in D.P.F Hurua-C-156 (41) — “Forest land use approved” on 12 Aug 2026.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.