More information requestedPower · Kinnaur, Himachal Pradesh

400 KV D/C Transmission Line (4.897 Km) From 450 MW Shongtong Hep to the Tower No-04 of 400 KV D/C Baspa II to Jhakri Transmission Line, District Kinnaur (H.P).

400 KV D/C Transmission Line (4.897 Km) From 450 MW Shongtong Hep to the Tower No-04 of 400 KV D/C Baspa II to Jhakri Transmission Line, District Kinnaur (H.P) is a proposed power project in Dakhaye (30/4), Kalpa, Kinnaur, Himachal Pradesh. The site covers 55.7 acres. Its stated project cost is ₹85.3 crore. As of 27 Nov 2026, its status is “More information requested” (since 10 Nov 2026).

See it on the live map All projects in Kinnaur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusMore information requested
Status since10 Nov 2026
Application filed7 Oct 2025
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantHp Power Transmission Corporation Limited
Land area55.7 acres (22.5 ha)
Forest land52.9 acres (21.4 ha)
Project cost₹85.3 crore
Village / localityDakhaye (30/4)
Taluk / tehsilKalpa
DistrictKinnaur
StateHimachal Pradesh
Location fromSite boundary on record
Our referenceWID-HP-00826

In context

1 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Dakhaye (30/4), Kalpa, Kinnaur, Himachal Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 5 Hp Power Transmission Corporation projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.