Projects by type
| Type | Projects |
|---|---|
| Mining | 82 |
| Roads & highways | 48 |
| Power | 8 |
| Buildings & townships | 4 |
| Telecom | 3 |
| Pipelines | 2 |
| Water & irrigation | 2 |
| Other | 2 |
| Waste management | 1 |
| Industry | 1 |
Where they are in the approval process
| Status | Projects |
|---|---|
| Filed or under review | 32 |
| In-principle approval | 4 |
| Approved | 73 |
| Not approved | 6 |
| Withdrawn or lapsed | 38 |
Recently approved
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Road Mokhampura To Madhopur Madhopura, Chhipabarod | Roads & highways | 6.2 acres | Forest land use approved | 19 Jun 2026 |
| Road to Sahariya Girls Residential School Kishanganj Kishanganj, Kishanganj | Roads & highways | 10.5 acres | Forest land use approved | 1 Mar 2023 |
| Road Rooparel to Mohammodpur Mohammadpur, Chhabra | Roads & highways | 6.9 acres | Forest land use approved | 20 Jun 2026 |
| Road Kalpa Jageer to Patlapani Kalpa, Chhipabarod | Roads & highways | 10 acres | Forest land use approved | 19 Jun 2026 |
| Road Janchrora to Gogatori Gugartori, Chhabra | Roads & highways | 3.5 acres | Forest land use approved | 19 Jun 2026 |
| Masonry Stone Mining Project, M.L.-05/2024 (Ref. No. 202410000112560), Area-1.1386… Ratanpura, Atru | Mining | 2.8 acres | Environmental approval granted | 10 Mar 2026 |
| 132kV S/C Transmission Line from Proposed 132kV GSS Devri to 132kV GSS Mamoni, District-… Pindasal, Shahbad | Power | 15.2 acres forest land | Forest land use approved | 10 Sept 2025 |
| Chainpuriya to Surajpuramal Surajpura Malkarni, Chhipabarod | Roads & highways | 13.3 acres | Forest land use approved | 21 Oct 2024 |
| Proposed Masonry Stone Mining Project, M.L. No. 01/2026, Reference No.:202610000145611,… Laroni, Kishanganj | Mining | 7.8 acres | Cleared for impact study | 22 Jun 2026 |
| Shri Jagdish Parsad Sharma, Masonary Stone mining Project (Plot No. 26), Lease area:… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 12 Jun 2026 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Proposed Masonry Stone Mining Project, M.L. No. 02/2024 (Ref. No. 202410000109076), Area… Badora, Atru | Mining | 2.6 acres | Initial checks | 24 Nov 2026 |
| This is a Fresh Proposal for Masonry Stone (Minor Mineral) Mining Project", {Ref. No.… Kishanganj, Kishanganj | Mining | 4.2 acres | Under environmental review | 27 Oct 2026 |
| M/s S And A Industries, Masonary Stone Mining Project, (Plot No. - 20), Lease Area -… Gordhanpura, Kishanganj | Mining | 2.5 acres | Under environmental review | 13 Aug 2026 |
| Masonry Stone Mining Project, M.L.-01/2024 (Ref. No. 202410000106653), Applied (L.O.I)… Gajron, Kishanganj | Mining | 3.2 acres | Lapsed | 18 Jul 2026 |
| WATER SUPPLY PROJECT FOR ENROUTE VILLAGES OF CHHABRA TEHSIL AND CHHIPABAROD TEHSIL FROM… Digod Khalsa, Chhipabarod | Pipelines | 6,209.3 acres | More information requested | 15 Jul 2026 |
| M/s Shree Balaji Stones, Masonary Stone Mining Project (M.L.No.02/2026 ), Lease Area-… Laroni, Kishanganj | Mining | 6 acres | Under environmental review | 13 Jul 2026 |
| Construction of Road Kadiyahat to Gadiyamaher Kadaiya Hat, Chhabra | Roads & highways | 47.2 acres | More information requested | 13 Jul 2026 |
| Construction of Puliya on Bhanwargarh to Nahargarh Road (Barni Nadi) Jaitpura, Kishanganj | Roads & highways | 17.1 acres | More information requested | 8 Jul 2026 |
| Masonry Stone Cluster Mining Project of LOI Plot No.- 19, Area- 1.0433 Ha., Cluster… Gordhanpura, Kishanganj | Mining | 2.6 acres | Under environmental review | 1 Jul 2026 |
| Proposed Masonry Stone Mining Project, Reference no. 202510000122050, M.L. No- 01/2025… Mau, Antah | Mining | 4.7 acres | Under environmental review | 30 Jun 2026 |
| M/s Shree Balaji Stones, Masonary Stone Mining Project (M.L.No.03/2026 & Reference… Laroni, Kishanganj | Mining | 3.2 acres | Under environmental review | 29 Jun 2026 |
| Proposed Masonry Stone Mining Project, M.L. No. 01/2026, Reference No.:202610000145611,… Laroni, Kishanganj | Mining | 7.8 acres | Cleared for impact study | 22 Jun 2026 |
| Mothpur Kerwaliya road to Devpura Devpura, Atru | Roads & highways | 9.9 acres | In-principle approval, conditions pending | 20 Jun 2026 |
| Road Rooparel to Mohammodpur Mohammadpur, Chhabra | Roads & highways | 6.9 acres | Forest land use approved | 20 Jun 2026 |
| Kaloni to Aamkoh Via Baint Amkhoh, Shahbad | Roads & highways | 54.1 acres | More information requested | 19 Jun 2026 |
| Construction of road Boren To Kharda To Pipalda Kharda, Shahbad | Roads & highways | 15.6 acres | In-principle approval, conditions pending | 19 Jun 2026 |
| Dikoniya Talawara road to Gajron Under PMGSY-IV YR. 2025-26 Gajron, Kishanganj | Roads & highways | 2.5 acres | In-principle approval, conditions pending | 19 Jun 2026 |
| Construction of Bichi to Suhan under PMGSY-IV Scheme Batch - I 2025-26 Mohanpura, Shahbad | Roads & highways | 13.8 acres | More information requested | 19 Jun 2026 |
| Construction of Road from Kedarkui to Muhal Kedar Kui, Shahbad | Roads & highways | 110.3 acres | In-principle approval, conditions pending | 19 Jun 2026 |
| Road Kalpa Jageer to Patlapani Kalpa, Chhipabarod | Roads & highways | 10 acres | Forest land use approved | 19 Jun 2026 |
| samraniya Ajrora Bahrai road to silori under PMGSY Scheme -IV 2025-26 Dhansuri, Shahbad | Roads & highways | 12.8 acres | More information requested | 19 Jun 2026 |
| Road Mokhampura To Madhopur Madhopura, Chhipabarod | Roads & highways | 6.2 acres | Forest land use approved | 19 Jun 2026 |
| Road Janchrora to Gogatori Gugartori, Chhabra | Roads & highways | 3.5 acres | Forest land use approved | 19 Jun 2026 |
| Shri Jagdish Parsad Sharma, Masonary Stone mining Project (Plot No. 26), Lease area:… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 12 Jun 2026 |
| Shri Jagdish Parsad Sharma, Masonary Stone mining Project (Plot No. 05), Lease area:… Gordhanpura, Kishanganj | Mining | 2.5 acres | Under environmental review | 12 Jun 2026 |
| Shri Manoj Kumar Sharma , Masonary Stone Mining Project (Plot No. 21) , lease area -… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 26 May 2026 |
| M/s V P Mining & Minerals, Masonary Stone Mining Project, (Plot No.12), Lease Area- 1.00… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 20 May 2026 |
| Ramgarh Barrage, Mahalpur Barrage, Navnera pump house, Rising Main up to Delivery… Digodpar, Kishanganj | Water & irrigation | 2,175.2 acres | More information requested | 5 May 2026 |
| The Work of Transmission Main, Wtp, Scada, Road Crossings, Forest Clearance, Vvnl for… Rampura, Kishanganj | Pipelines | 22.9 acres | Lapsed | 30 Apr 2026 |
| 132 KV S/C Kolukheri-Manoharthana Transmission Line Total Length of Line - 52.205 KM… Paroliya, Chhabra | Power | 36 acres forest land | More information requested | 18 Apr 2026 |
| Masonry Stone Cluster Mining Project of LOI Plot No.- 7, Area- 1.0 Ha., Cluster Area:-… Gordhanpura, Kishanganj | Mining | 2.5 acres | Environmental approval granted | 28 Mar 2026 |
| Masonry Stone Mining Project, M.L.-05/2024 (Ref. No. 202410000112560), Area-1.1386… Ratanpura, Atru | Mining | 2.8 acres | Environmental approval granted | 10 Mar 2026 |
| Construction of Bridge on Bhansasur Banganga River Danta (Sitabari), Shahbad | Roads & highways | 12.1 acres | Lapsed | 26 Feb 2026 |
| Proposed Masonry Stone Mining Project, M.L.-05/2024, Applied (L.O.I) Area-1.1386… Ratanpura, Atru | Mining | 2.8 acres | Under environmental review | 20 Feb 2026 |
| Masonry Stone Cluster Mining Project of LOI Plot No.- 3, Area- 1.0 Ha., Cluster Area:-… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 4 Feb 2026 |
| Masonry Stone Cluster Mining Project of LOI Plot No.- 25, Area- 1.0 Ha.,Cluster Area:-… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 31 Jan 2026 |
| Masonry Stone Cluster Mining Project, LOI Plot No.- 1, Area- 1.0 Ha., Cluster Area:-… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 31 Jan 2026 |
| Application ToR (Term of Reference) of Masonry Stone Cluster Mining Project, LOI Plot… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 29 Jan 2026 |
| Masonry Stone Cluster Mining Project, LOI Plot No.- 6, Area- 1.0 Ha., Cluster Area:-… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 29 Jan 2026 |
| Masonry Stone (M-Sand) Mining Project of LOI Plot No.- 9, Area- 1.0 Ha., Cluster… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 29 Jan 2026 |
| Masonry Stone (M-Sand) Mining Project of LOI Plot No.- 8, Area- 1.0466 Ha., Cluster… Gordhanpura, Kishanganj | Mining | 2.6 acres | Cleared for impact study | 29 Jan 2026 |
| Proposed Project for River Bed Sand Mining (Bajri) Plot No.BJ-04/2024 for Mineral River… Chothya, Atru | Mining | 54.8 acres | Under environmental review | 26 Dec 2025 |
| Proposed Project for River Bed Sand Mining (Bajri) Plot No.BJ-04/2024 for Mineral River… Chothya, Atru | Mining | 54.8 acres | Lapsed | 26 Dec 2025 |
| Application ToR (Term of Reference) of Masonry Stone Cluster Mining Project, LOI Plot… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 14 Nov 2025 |
| Application for ToR for Masonry Stone Cluster Mining Project of LOI Plot No.- 11, Area-… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 14 Nov 2025 |
| Jai Mata Di Stones Bilendi, Antah | Mining | 3 acres | Lapsed | 2 Nov 2025 |
| Proposed Project of Bajri (River Sand) Minor Mineral Mining Project, Plot No.-… Bamori, Atru | Mining | 110.5 acres | Under environmental review | 16 Oct 2025 |
| Shri Jagdish Prasad Sharma, Plot No. 23, Masonary Stone mining Project, Lease Area:… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 24 Sept 2025 |
| Shri Jagdish Prasad Sharma, Plot No. 24, Masonary Stone mining Project, Lease Area:… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 24 Sept 2025 |
| Shri Manoj Kumar Sharma, Masonary Stone Mining Project, (Plot No. - 14), Lease Area -… Gordhanpura, Kishanganj | Mining | 2.5 acres | Cleared for impact study | 23 Sept 2025 |
Questions people ask
How many projects are planned in Baran?
153 projects in Baran have applied for approval since January 2022. 109 of them are active (not withdrawn, lapsed or rejected) and 36 are still awaiting a decision.
What was approved most recently in Baran?
Road Mokhampura To Madhopur in Madhopura — “Forest land use approved” on 5 Nov 2026.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.
Most active developers in Baran
- PWPublic Works Department, Rajasthan in Baran32
- RRRajasthan Rajya Vidyut Prasaran Nigam LTD Kota in Baran5
Adani Power in Baran3- RRRajasthan Rajya Vidhyut Utpadan Nigam2
Jio Digital Fibre2
Bharat Sanchar Nigam (BSNL)2