| Status | Projects |
|---|---|
| Filed or under review | 1 |
| Approved | 10 |
| Withdrawn or lapsed | 2 |
Recently approved
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Proposed Expansion of Iron Foundry Unit from 53400 TPA to 92100 TPA (Ferrous Castings)… Kurudampalaiyam, Coimbatore North | Industry | 15.7 acres | Environmental approval granted | 19 Mar 2026 |
| Proposed expansion of foundry unit Chettiyakkapalaiyam, Kinathukadavu | Industry | 43.5 acres | Environmental approval granted | 2 Mar 2026 |
| Proposed Expansion of Madukkarai Cement Grinding Unit and Packing unit with cement… Madhukkarai, Madukkari | Industry | 146.5 acres | Cleared for impact study | 18 Sept 2024 |
| Amendment in Environmental Clearance by Everest Industries Limited Kurichi, Madukkari | Industry | 58.9 acres | Environmental approval granted | 29 Aug 2025 |
| Proposed expansion of foundry unit Chettiyakkapalaiyam, Kinathukadavu | Industry | 43.5 acres | Environmental approval granted | 16 Jul 2025 |
| Proposed expansion of Ferrous Casting from 19200 TPA to 74400 TPA by M/s. Aquasub… Kallapalaiyam, Sulur | Industry | 36.9 acres | Environmental approval granted | 26 Jul 2024 |
| Proposed expansion of Ferrous Casting from 19200 TPA to 74400 TPA by M/s. Aquasub… Kallapalaiyam, Sulur | Industry | 36.9 acres | Cleared for impact study | 23 Nov 2023 |
| Proposed expansion of foundry unit located at S.F. No. 478/1 & 2, Ponnandampalayam,… Kaniyur, Sulur | Industry | 5.6 acres | Cleared for impact study | 18 Oct 2023 |
| Existing Standalone Steel Rolling Mill located at S.F. No. 308/1G2, 309/1A, 316/1F1 &… Devanampalaiyam, Kinathukadavu | Industry | 4.1 acres | Cleared for impact study | 1 Sept 2023 |
| Proposed expansion of foundry unit Orattukkuppai, Madukkari | Industry | 45.9 acres | Cleared for impact study | 6 Apr 2023 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Proposed Expansion of Iron Foundry Unit from 53400 TPA to 92100 TPA (Ferrous Castings)… Kurudampalaiyam, Coimbatore North | Industry | 15.7 acres | Environmental approval granted | 19 Mar 2026 |
| Proposed expansion of foundry unit Chettiyakkapalaiyam, Kinathukadavu | Industry | 43.5 acres | Environmental approval granted | 2 Mar 2026 |
| Amendment in Environmental Clearance by Everest Industries Limited Kurichi, Madukkari | Industry | 58.9 acres | Environmental approval granted | 29 Aug 2025 |
| Proposed Expansion of the Existing Paper Mill to Increase the Paper Board Production… Kemmarampalaiyam, Mettupalayam | Industry | 411 acres | Lapsed | 28 Aug 2025 |
| Proposed expansion of foundry unit Chettiyakkapalaiyam, Kinathukadavu | Industry | 43.5 acres | Environmental approval granted | 16 Jul 2025 |
| Proposed Expansion of Iron Foundry Unit from 53400 TPA to 92100 TPA (C.I. Castings) by… Kurudampalaiyam, Coimbatore North | Industry | 15.7 acres | Returned to applicant | 8 Apr 2025 |
| Proposed Expansion of Madukkarai Cement Grinding Unit and Packing unit with cement… Madhukkarai, Madukkari | Industry | 146.5 acres | Cleared for impact study | 18 Sept 2024 |
| Proposed expansion of Ferrous Casting from 19200 TPA to 74400 TPA by M/s. Aquasub… Kallapalaiyam, Sulur | Industry | 36.9 acres | Environmental approval granted | 26 Jul 2024 |
| Existing Standalone Steel Rolling Mill located at S.F. No. 356/3B, 349, Idigarai… Idigarai, Annur | Industry | 3.4 acres | Lapsed | 8 Mar 2024 |
| Proposed expansion of Ferrous Casting from 19200 TPA to 74400 TPA by M/s. Aquasub… Kallapalaiyam, Sulur | Industry | 36.9 acres | Cleared for impact study | 23 Nov 2023 |
| Proposed expansion of foundry unit located at S.F. No. 478/1 & 2, Ponnandampalayam,… Kaniyur, Sulur | Industry | 5.6 acres | Cleared for impact study | 18 Oct 2023 |
| Existing Standalone Steel Rolling Mill located at S.F. No. 308/1G2, 309/1A, 316/1F1 &… Devanampalaiyam, Kinathukadavu | Industry | 4.1 acres | Cleared for impact study | 1 Sept 2023 |
| Proposed expansion of foundry unit Orattukkuppai, Madukkari | Industry | 45.9 acres | Cleared for impact study | 6 Apr 2023 |
Questions people ask
How many industry projects are planned in Coimbatore?
13 industry projects in Coimbatore have applied for approval since January 2022. 11 of them are active (not withdrawn, lapsed or rejected) and 1 are still awaiting a decision.
What was approved most recently in Coimbatore?
Proposed Expansion of Iron Foundry Unit from 53400 TPA to 92100 TPA (Ferrous Castings) and 6000 TPA (Non-Ferrous Castings) (Total – 98100 TPA) by M/s. Aquasub Engineering Unit - IV, Foundry - II in Kurudampalaiyam — “Environmental approval granted” on 7 Sept 2026.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.