Project details
| Official title | Construction of Check Weirs across Nallah including 01 no Pump house at Tushnabad |
|---|---|
| Status | Forest land use approved |
| Status since | 22 Apr 2026 |
| Application filed | 24 May 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Other |
| Applicant | Executive Engineer Rcd Apwd Wimberlygunj |
| Land area | 300 m² |
| Forest land | 330 m² |
| Project cost | ₹2.1 crore |
| Village / locality | Mitha Khari |
| Taluk / tehsil | Ferrargunj |
| District | South Andaman |
| State | Andaman and Nicobar Islands |
| Location from | Site boundary on record |
| Our reference | WID-AN-00050 |
In context
8 applications in South Andaman since January 2022 are in the same category (Other): 5 approved, 1 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 18 months from filing to approval.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mitha Khari, Ferrargunj, South Andaman, Andaman and Nicobar Islands. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Check Weir across Nallah Including 01 no pump House at Tushnabad — lapsed, 650 m away
- 40MW ground-based Solar Photovoltaic (PV) Power Plant — more information requested, 3 km away
- Proposed development of Viper Island — lapsed, 5.1 km away
- 60MW Floating Solar Photovoltaic (PV) Power Plant — under coastal review, 7.3 km away
- 04-Lane Major Bridge for Connectivity of Sri Vijaya Puram (Earlier Known As… — lapsed, 7.7 km away
- Gas Supply Infrastructure for Power Project at Sri Vijayapuram, Hopetown — cleared for impact study, 8.1 km away
- Gas Supply Infrastructure for Power Project at Sri Vijayapuram, Hopetown — lapsed, 8.1 km away
- 57.105 MW Single Fuel (LNG) based Power Project at Hope Town (V), Ferrargunj… — under environmental review, 8.2 km away
More from Executive Engineer Rcd Apwd Wimberlygunj in South Andaman
- Check Weir, Pump house, Pipeline & 01 No. CWR (2.45 Lakh) at Shoalbay-14 under… — in-principle approval, conditions pending
- Check Weir, Pump house and pipeline & 01 No. CWR (2.45 Lakh) at Shoal Bay-11… — in-principle approval, conditions pending
- Check Weir across Nallah Including 01 no pump House at Tushnabad — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.