Quick answers
What is this project?
Installation of One 4G Tower in Strait Island under USOF Project is an approved telecom project in Strait Island, Rangat, North & Middle Andaman, Andaman and Nicobar Islands. The site covers 0.1 acres.
Who is building it?
The applicant is Office of the Joint Controller of Communication Accounts Dot Andaman and Nicobar Circle.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 22 Nov 2023), as of 27 Nov 2026.
Where is it?
In Strait Island, Rangat, North & Middle Andaman, Andaman and Nicobar Islands.
How big is it?
It has a stated cost of ₹1.1 crore; a site of 0.1 acres and 400 m² of forest land.
When was it filed?
The application was filed on 20 Jun 2023.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 22 Nov 2023 |
| Application filed | 20 Jun 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Telecom |
| Applicant | Office of the Joint Controller of Communication Accounts Dot Andaman and Nicobar Circle |
| Land area | 400 m² |
| Forest land | 400 m² |
| Project cost | ₹1.1 crore |
| Village / locality | Strait Island |
| Taluk / tehsil | Rangat |
| District | North & Middle Andaman |
| State | Andaman and Nicobar Islands |
| Location from | Site boundary on record |
| Our reference | WID-AN-00087 |
In context
16 applications in North & Middle Andaman since January 2022 are in the same category (Telecom): 6 approved, 1 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 0.1 acres, this one is smaller than 100% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Strait Island, Rangat, North & Middle Andaman, Andaman and Nicobar Islands. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- USOF Project for 4G Mobile Coverage in Uncovered Villages and NH in Andaman &… — lapsed, 0 m away
- 4g Saturation Project in Andaman and Nicobar Islands — forest land use approved, 7.7 km away
- Diversion of 0.2207 Ha Forest Land for Construction of Two Minor Bridges in… — forest land use approved, 13.8 km away
- Diversion of Forest Land for Laying Optical Fibre Cable in Baratang Forest… — forest land use approved, 14 km away
- Diversion of Forest Land for Laying Optical Fibre Cable in Baratang Forest… — lapsed, 14 km away
- Baratang — lapsed, 14.5 km away
- Providing Passenger Amenities and Renovation of Office Cum Transit… — coastal clearance granted, 16.8 km away
- Extension of jetty by 150m x 20m and 8 Navigational aids at Long Island in… — coastal clearance granted, 16.9 km away
More from Office of the Joint Controller of Communication Accounts Dot Andaman and Nicobar Circle in North & Middle Andaman
- Optical Fibre Laying in between Middle Strait to Baratang Jetty — coastal clearance granted
- Diversion of forest land for laying of Optical Fibre Cable from Kishori Nagar… — lapsed
- Proposal to Divert 0.4707 Ha of Forest Land for Laying a 26.49 Km Ofc Cable in… — forest land use approved
- Three (3) 4G towers in Mayabunder Forest Division — forest land use approved
- Diversion of Forest Land for Laying Optical Fibre Cable in Mayabunder Forest… — forest land use approved
- Diversion of Forest Land for Laying Optical Fibre Cable in Baratang Forest… — forest land use approved
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.