One of 2 filings for this project. The project's main page, with every filing and where each stands: Kamalapadu Pumped Storage Hydro Project (950 MW)
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 7 Aug 2023 |
| Application filed | 24 May 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Water & irrigation |
| Applicant | New and Renewable Energy Development Corporation of Andhra Pradesh LTD (Nredcap) |
| Land area | 3,058.8 acres (1,237.9 ha) |
| Project cost | ₹4,676.5 crore |
| Village / locality | Kamalapadu |
| Taluk / tehsil | Yadiki |
| District | Anantpur |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-00728 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 24 Apr 2025 | Cleared for impact study | 3,058.8 acres | ₹4,676.5 crore |
| Early planning filed 24 May 2023 (this page) | Cleared for impact study | 3,058.8 acres | ₹4,676.5 crore |
In context
5 applications in Anantpur since January 2022 are in the same category (Water & irrigation): 4 approved, 0 filed or under review, and 1 withdrawn, lapsed or rejected.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kamalapadu, Yadiki, Anantpur, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Kamalapadu Pumped Storage Hydro Project (950 MW) — cleared for impact study, 0 m away
- Kamalapadu Closed Loop Pumped Storage Hydro Project — environmental approval granted, 650 m away
- Sri A. Mahesh Kumar Reddy, Quarry lease over an extent of 4.674 Ha — under environmental review, 2.2 km away
- Environmental Clearance for the Amalgamated Gudipadu Limestone Mine of M/s.… — lapsed, 3.6 km away
- Gudipadu Limestone Mine (Limestone Production: 4.70 MTPA with Total Excavation… — environmental approval granted, 5.7 km away
- Amendment in Environmental Clearance for Extension of the time period for… — environmental approval granted, 5.8 km away
- Amendment in Environmental Clearance for Extension of the Time Period for… — returned to applicant, 5.8 km away
- M/s. Sri Satya Sai Mineral Company (Konuppalpadu Limestone Mine) — more information requested, 6.7 km away
6 New & Renewable Energy Development Corporation of Andhra Pradesh projects in Anantpur
All 32 New & Renewable Energy Development Corporation of Andhra Pradesh projects across India