Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 16 Apr 2025 |
| Application filed | 26 Mar 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Royalty Inspector DMGO Kadapa |
| Land area | 42 acres (17 ha) |
| Project cost | ₹17 lakh |
| Village / locality | Vempalli |
| Taluk / tehsil | Vempalle |
| District | Y.S.R. |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-02915 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 26 Mar 2025 (this page) | Environmental approval granted | 42 acres | ₹17 lakh |
| Early planning filed 20 Mar 2024 | Cleared for impact study | 42 acres | ₹17 lakh |
In context
139 applications in Y.S.R. since January 2022 are in the same category (Mining): 106 approved, 8 filed or under review, and 25 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 42 acres, this one is larger than 75% of them.
No other mining lease on record is within 500 m of this site; 5 have applied within 5 km.
Where it is
Vempalli, Vempalle, Y.S.R., Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Vempalli Sand Reach — cleared for impact study, 0 m away
- Tangedupalli Sand Reach — environmental approval granted, 1.7 km away
- Tangedupalli Sand Reach — cleared for impact study, 1.7 km away
- Tangedupalli Sand Reach — environmental approval granted, 2.1 km away
- Kothagangireddipalli-II — environmental approval granted, 3.2 km away
- Kothagangireddy Palli Sand Reach — environmental approval granted, 3.5 km away
- Kothagangireddy Palli Sand Reach — cleared for impact study, 3.5 km away
- Mining project by M/s RRR Transport, Managing Partner: Sri Rajula Ramanjaneya… — environmental approval granted, 3.5 km away
More from Royalty Inspector DMGO Kadapa in Y.S.R.
- Venkayyakalva Sand Reach - 20 Ha — cleared for impact study
- Sambatur Open Sand Reach — environmental approval granted
- Marellamadaka-II Open Sand Reach — environmental approval granted
- Kondavandlapalli Open Sand Reach — cleared for impact study
- Goriganur Sand Reach — environmental approval granted
- Goriganur Sand Reach — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.