Quick answers
What is Mining project by M/s GRK Minerals?
This proposed mining project by M/s GRK Minerals is in Govardhanapuram, Saravakota, Srikakulam, Andhra Pradesh. The site covers 7.8 acres.
Who is building it?
The applicant is Gottipati Harsha Vardhan.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 10 Nov 2026), as of 27 Nov 2026.
Where is it?
In Govardhanapuram, Saravakota, Srikakulam, Andhra Pradesh.
How big is it?
It has a stated cost of ₹1 crore and a site of 7.8 acres.
When was it filed?
The application was filed on 16 Sept 2026.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 10 Nov 2026 |
| Application filed | 16 Sept 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Gottipati Harsha Vardhan |
| Land area | 7.8 acres (3.2 ha) |
| Project cost | ₹1 crore |
| Village / locality | Govardhanapuram |
| Taluk / tehsil | Saravakota |
| District | Srikakulam |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-03846 |
In context
286 applications in Srikakulam since January 2022 are in the same category (Mining): 209 approved, 37 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 7.8 acres, this one is smaller than 64% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 45.4 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 28 mining leases have applied within 5 km.
Where it is
Govardhanapuram, Saravakota, Srikakulam, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Kum. Chinnala Syamala Saranya — under environmental review, 200 m away
- Mining project by M/s Avenir Granites — more information requested, 400 m away
- Mining project by M/s Avenir Granites — cleared for impact study, 400 m away
- Sri Phanindra Kamepalli — under environmental review, 400 m away
- Kum. Chinnala Syamala Saranya — cleared for impact study, 400 m away
- Mining project by M/s. Avenir Granites — under environmental review, 450 m away
- Mining project by M/s Avenir Granites Mgptr: Sri Dodda Mahesh, Extent: 5.066… — under environmental review, 450 m away
- M/s. Avenir Granites Mg.Ptr.Sri Dodda Mahesh Mining of Colour Granite (variety… — environmental approval granted, 600 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.