Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 29 May 2023 |
| Application filed | 29 May 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Divisional Forest Officer |
| Land area | 37.1 acres (15 ha) |
| Project cost | ₹1.5 crore |
| Village / locality | Nakhula Pahar |
| Taluk / tehsil | Mayong |
| District | Morigaon |
| State | Assam |
| Location from | Site boundary on record |
| Our reference | WID-AS-00256 |
In context
32 applications in Morigaon since January 2022 are in the same category (Mining): 18 approved, 5 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 37.1 acres, this one is larger than 88% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 150.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 7 mining leases have applied within 5 km.
Where it is
Nakhula Pahar, Mayong, Morigaon, Assam. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Jagiroad Stone Contract Area No. F(5) — lapsed, 100 m away
- Jagiroad Stone Mining Area No. F (6) — in-principle approval, conditions pending, 350 m away
- Jagiroad Stone Mining Area No. F (6), (Reserve Forest Area) at Sonaikuchi… — cleared for impact study, 350 m away
- Jagiroad Stone Mahal No. F (1) — lapsed, 650 m away
- Jagiroad Stone Mahal No. F1 — in-principle approval, conditions pending, 650 m away
- Proposed Jagiroad Stone Contract Area No. : F(4), (R.F)at Sonaikuchi Reserve… — cleared for impact study, 650 m away
- Jagiroad Stone Mahal No. F (1) — lapsed, 650 m away
- Jagiroad Stone Mahal No. F (1) — environmental approval granted, 650 m away
More from Divisional Forest Officer in Morigaon
- Jagiroad Stone Contract Area No. F(5) — lapsed
- Balakuchi Sand Permit Area in (Rev. Portion) — lapsed
- Borkuloi-Boha Sand Mahal Part-I (Rev. Portion) on Kopili River Bed — environmental approval granted
- Dhamkhunda-Hatibagora Sand Mahal Part-II (Rev. Portion) — environmental approval granted
- Boha Sand Mining Permit Area (Rev. Portion) on Kopili River Bed — environmental approval granted
- Nakhula Beat Sand Permit Area No. 4(Rev. Portion) — environmental approval granted
About this information