Project details
| Status | Lapsed |
|---|---|
| Status since | 21 May 2025 |
| Application filed | 4 Apr 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Divisional Forest Officer |
| Land area | 12.4 acres (5 ha) |
| Project cost | ₹3.3 crore |
| Village / locality | Nakhola Pahar |
| Taluk / tehsil | Mayong |
| District | Morigaon |
| State | Assam |
| Location from | Site boundary on record |
| Our reference | WID-AS-00616 |
In context
32 applications in Morigaon since January 2022 are in the same category (Mining): 18 approved, 5 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 12.4 acres, this one is larger than 75% of them.
3 other mining leases have applied within 500 m of this site; together with this one they cover 150.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 7 mining leases have applied within 5 km.
Where it is
Nakhola Pahar, Mayong, Morigaon, Assam. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Jagiroad Stone Contract Area No. : F(5), (R.F)at Sonaikuchi Reserve… — cleared for impact study, 100 m away
- Jagiroad Stone Mining Area No. F (6) — in-principle approval, conditions pending, 300 m away
- Jagiroad Stone Mining Area No. F (6), (Reserve Forest Area) at Sonaikuchi… — cleared for impact study, 300 m away
- Proposed Jagiroad Stone Contract Area No. : F(4), (R.F)at Sonaikuchi Reserve… — cleared for impact study, 600 m away
- Jagiroad Stone Mahal No. F1 — in-principle approval, conditions pending, 650 m away
- Jagiroad Stone Mahal No. F (1) — lapsed, 650 m away
- Jagiroad Stone Mahal No. F (1) — lapsed, 700 m away
- Jagiroad Stone Mahal No. F (1) — environmental approval granted, 700 m away
More from Divisional Forest Officer in Morigaon
- Balakuchi Sand Permit Area in (Rev. Portion) — lapsed
- Borkuloi-Boha Sand Mahal Part-I (Rev. Portion) on Kopili River Bed — environmental approval granted
- Dhamkhunda-Hatibagora Sand Mahal Part-II (Rev. Portion) — environmental approval granted
- Boha Sand Mining Permit Area (Rev. Portion) on Kopili River Bed — environmental approval granted
- Nakhula Beat Sand Permit Area No. 4(Rev. Portion) — environmental approval granted
- "boha Sand Mining Permit Area(Rev. Portion)" on Kopili River Bed — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.