Quick answers
What is this project?
Expansion of Pirpainti Thermal Power Plant from 2400(3x800) MW (Phase I) to 4800 MW by adding 2400(3x800) MW Ultra Super Critical TPP under Phase II in the Existing Area at Sirmatpur, Harinkol, Mundwa urf Tundwa, Sundarpur and Adjacent Villages is a withdrawn power project in Mariakol G.P., Pirpainti, Bhagalpur, Bihar. The site covers 1,183.6 acres.
Who is building it?
The applicant is Adani Power Limited.
Has it been approved?
No. The application was withdrawn on 28 Aug 2026, so it is no longer under consideration.
Where is it?
In Mariakol G.P., Pirpainti, Bhagalpur, Bihar.
How big is it?
It has a stated cost of ₹561.8 crore and a site of 1,183.6 acres.
When was it filed?
The application was filed on 28 Aug 2026.
Project details
| Official title | Expansion of Pirpainti Thermal Power Plant from 2400(3x800) MW (Phase I) to 4800 MW by adding 2400(3x800) MW Ultra Super Critical TPP under Phase II in the Existing Area at Sirmatpur, Harinkol, Mundwa urf Tundwa, Sundarpur and Adjacent Villages in Tehsil/Block Pirpainti, District Bhagalpur, Bihar by Adani Power Limited |
|---|---|
| Status | Withdrawn |
| Status since | 28 Aug 2026 |
| Application filed | 28 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Power |
| Applicant | Adani Power Limited |
| Land area | 1,183.6 acres (479 ha) |
| Project cost | ₹561.8 crore |
| Village / locality | Mariakol G.P. |
| Taluk / tehsil | Pirpainti |
| District | Bhagalpur |
| State | Bihar |
| Location from | Site area on record |
| Our reference | WID-BR-02486 |
In context
6 applications in Bhagalpur since January 2022 are in the same category (Power): 2 approved, 3 filed or under review, and 1 withdrawn, lapsed or rejected.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mariakol G.P., Pirpainti, Bhagalpur, Bihar. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Pirpainti Thermal Power Plant from 2400(3x800) MW (Phase I) to… — under environmental review, 0 m away
- Proposed 2400 (3x800)MW Coal Based Ultra Super Critical Thermal Power Project… — environmental approval granted, 100 m away
- Proposed 2400 (3x800)MW Coal Based Ultra Super Critical Thermal Power Project… — cleared for impact study, 100 m away
- M/S G S B Udyog Proposed Brick Clay Mining Project at Mauza- Harin Kol, Block-… — environmental approval granted, 1.7 km away
- M/s Ram Swaroop Ceramics Marks - RSC Proposed Brick clay Mining Project at… — environmental approval granted, 2.3 km away
- Proposed Brick Earth Mining for M/S A M R BRICKS - Imamnagar Soil Brick Mining… — environmental approval granted, 2.4 km away
- Brick Earth Mining project of M/s P.A.G. Bricks at Mauza- Imamnagar, Block-… — environmental approval granted, 2.8 km away
- M/S W. B. B. Bricks Proposed Brick Clay Mining Project at Mauza- Manikpur,… — environmental approval granted, 3.9 km away
More from Adani Power Limited in Bhagalpur
- Expansion of Pirpainti Thermal Power Plant from 2400(3x800) MW (Phase I) to… — under environmental review
- Proposed 2400 (3x800)MW Coal Based Ultra Super Critical Thermal Power Project… — environmental approval granted
- Proposed 2400 (3x800)MW Coal Based Ultra Super Critical Thermal Power Project… — cleared for impact study
4 Adani Power projects in Bhagalpur
All 68 Adani Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.