Quick answers
What is this project?
Greenfield Project of Iron Ore Pelletization Plant (9,00,000 TPA), Sponge Iron (2,31,000 TPA), MS Billets (2,04,000 MTPA), Rolling Mill (I , 98,000 TPA) with Captive Power Plant (24 MW) by M/s. Saar Steel & Power Private Limited is an approved industrial project in Chaple, Kharsia, Raigarh, Chhattisgarh. The site covers 50.1 acres.
Who is building it?
The applicant is M/S Saar Steel & Power PVT LTD.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 13 Sept 2023), as of 27 Nov 2026.
Where is it?
In Chaple, Kharsia, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹385 crore and a site of 50.1 acres.
When was it filed?
The application was filed on 14 Jul 2023.
Project details
| Official title | Greenfield Project of Iron Ore Pelletization Plant (9,00,000 TPA), Sponge Iron (2,31,000 TPA), MS Billets (2,04,000 MTPA), Rolling Mill (I , 98,000 TPA) with Captive Power Plant (24 MW) located at Village- Kunkuni (Near ROB Railway Station), Tehsil- Kharsia, District-Raigarh, Chhattisgarh by M/s. Saar Steel & Power Private Limited |
|---|---|
| Status | Environmental approval granted |
| Status since | 13 Sept 2023 |
| Application filed | 14 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | M/S Saar Steel & Power PVT LTD |
| Land area | 50.1 acres (20.3 ha) |
| Project cost | ₹385 crore |
| Village / locality | Chaple |
| Taluk / tehsil | Kharsia |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00778 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 50.1 acres, this one is smaller than 60% of them.
23 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Chaple, Kharsia, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Greenfield Project of Iron Ore Pelletization Plant (9,00,000 TPA), Sponge Iron… — lapsed, 0 m away
- Greenfield Project of Wet Type Coal Washery based on Heavy Media cyclone of… — environmental approval granted, 600 m away
- Greenfield Project of Wet Type Coal Washery based on Heavy Media cyclone of… — cleared for impact study, 600 m away
- Proposed Greenfield Integrated Steel Plant with Iron Ore Beneficiation Plant… — cleared for impact study, 2.1 km away
- Santosh Kumar Dewangan — environmental approval granted, 2.1 km away
- Expansion of Sponge Iron from 120000 TPA to 144000 TPA and Billet from 100000… — environmental approval granted, 3.3 km away
- Expansion of existing Sponge Iron from 120000TPA to 168000TPA, Billet from… — withdrawn, 3.3 km away
- Amendment in Environment Clearance for Reduction in Plant Area From Proposed… — environmental approval granted, 3.3 km away
More from M/S Saar Steel & Power PVT LTD in Raigarh
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.