One of 3 filings for this project. The project's main page, with every filing and where each stands: Sikaser 1200 MW Pumped Storage Hydro-electric Project
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 26 Dec 2024 |
| Application filed | 18 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Water & irrigation |
| Applicant | Chhattisgarh State Power Generation Company Limited |
| Land area | 395.4 acres (160 ha) |
| Project cost | ₹5,118 crore |
| Village / locality | Pandripani |
| Taluk / tehsil | Bindranavagarh(Gariyaband) |
| District | Gariaband |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-01319 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 30 Dec 2025 | Forest land use approved | 395.4 acres | ₹5,118 crore |
| New project filed 8 May 2025 | Lapsed | 395.4 acres | ₹5,118 crore |
| Early planning filed 18 Nov 2024 (this page) | Cleared for impact study | 395.4 acres | ₹5,118 crore |
In context
5 applications in Gariaband since January 2022 are in the same category (Water & irrigation): 1 approved, 2 filed or under review, and 2 withdrawn, lapsed or rejected.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Pandripani, Bindranavagarh(Gariyaband), Gariaband, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sikaser 1200 MW Pumped Storage Hydro-electric Project — forest land use approved, 0 m away
- Sikaser 1200 MW Pumped Storage Hydro-electric Project — lapsed, 0 m away
- Sikaser Pumped Storage Hydro-electric Project (1200 MW) — lapsed, 1.2 km away
- Road construction work Dhawalpur to Kukarar, Udanti Sitanadi Tiger Reserve… — under wildlife review, 13.5 km away
- A65 Battalion Central Reserve Police Force Camp — decision issued, 13.6 km away
- Dhawalpur to Kukarar, Udanti Sitanadi Tiger Reserve Gariaband — more information requested, 14.6 km away
- Dhawalpur to Kukarar, Udanti Sitanadi Tiger Reserve Gariaband — more information requested, 14.6 km away
- Barula Sand Mine — lapsed, 24.1 km away
More from Chhattisgarh State Power Generation Company Limited in Gariaband
4 Chhattisgarh State Power projects in Gariaband
All 30 Chhattisgarh State Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.