| Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking Exemption… Darri, Korba, Chhattisgarh | Power | 1,744.5 acres | Under environmental review | 16 Nov 2026 |
| Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking Exemption… Darri, Korba, Chhattisgarh | Power | 1,744.5 acres | More information requested | 26 Oct 2026 |
| 2x250MW,Thermal Power Plant at Korba (East), Chhattisgarh of M/s Chhattisgarh State… Korba, Korba, Chhattisgarh | Power | 155 acres | Returned to applicant | 23 Sept 2026 |
| 2x250 MW , Thermal Power Plant at Korba (East), Chhattisgarh of M/s Chhattisgarh State… Korba, Korba, Chhattisgarh | Power | 155 acres | Returned to applicant | 31 Aug 2026 |
| 2x250 MW , Thermal Power Plant, Chhattisgarh State Electricity Board (CSEB) Korba East Korba, Korba, Chhattisgarh | Power | 155 acres | Withdrawn | 27 Aug 2026 |
| Kotpali Pumped Storage Hydro-electric Project (1800 MW) Joka, Balrampur, Chhattisgarh | Power | 16,510.8 acres | Forest land use approved | 21 Jun 2026 |
| Proposed Expansion by addition of 2 x 660 MW Supercritical Units of Chhattisgarh State… Jhabu, Korba, Chhattisgarh | Power | 1,744.5 acres | More information requested | 29 May 2026 |
| Amendment of 2x250 MW coal based Thermal Power Plant as per MOEF&CC notification dated… Korba, Korba, Chhattisgarh | Power | 155 acres | Lapsed | 9 Mar 2026 |
| Amendment of 1x500 MW coal based Thermal Power Plant as per MOEF&CC notification dated… Jhabu, Korba, Chhattisgarh | Power | 1,744.5 acres | Lapsed | 5 Feb 2026 |
| Rouni 2100 MW Pumped Storage Project Bhadikona, Jashpur, Chhattisgarh | Other | 8,066.3 acres | Forest land use approved | 3 Feb 2026 |
| Drilling of 10 Nos Boreholes for Proposed Dangari 1400 MW Pumped Storage Hydro Electric… Dangari, Jashpur, Chhattisgarh | Power | 992.7 acres | Forest land use approved | 3 Feb 2026 |
| Sikaser 1200 MW Pumped Storage Hydro-electric Project Pandripani, Gariaband, Chhattisgarh | Power | 395.4 acres | Forest land use approved | 30 Dec 2025 |
| Chhattisgarh State Power Companies Head Office Tuta, Raipur, Chhattisgarh | Buildings & townships | 2.5 acres | Environmental approval granted | 29 Sept 2025 |
| Rouni 2100 MW Pumped Storage Project Bhadikona, Jashpur, Chhattisgarh | Other | ₹7,643.9 crore | Lapsed | 18 Jul 2025 |
| Drilling of 10 Nos Boreholes for Proposed Dangari 1400 MW Pumped Storage Hydro Electric… Dangari, Jashpur, Chhattisgarh | Power | 992.7 acres | Lapsed | 18 Jul 2025 |
| Sikaser 1200 MW Pumped Storage Hydro-electric Project Pandripani, Gariaband, Chhattisgarh | Power | 395.4 acres | Lapsed | 8 May 2025 |
| HASDEO BANGO 800 MW PSP (Survey & Investigations) Lam Pahar P F, Korba, Chhattisgarh | Survey & exploration | 7,779 acres | Lapsed | 11 Apr 2025 |
| Kotpali Pumped Storage Hydro-electric Project (1800 MW) Joka, Balrampur, Chhattisgarh | Water & irrigation | 16,510.8 acres | Cleared for impact study | 4 Mar 2025 |
| Sikaser 1200 MW Pumped Storage Hydro-electric Project Pandripani, Gariaband, Chhattisgarh | Water & irrigation | 395.4 acres | Cleared for impact study | 18 Nov 2024 |
| Sikaser Pumped Storage Hydro-electric Project (1200 MW) East Raipur Pf, Gariaband, Chhattisgarh | Water & irrigation | 1,672.9 acres | Lapsed | 11 Oct 2024 |
| Proposed Expansion by addition of 2 x 660 MW Supercritical Units of Chhattisgarh State… Birbhat, Korba, Chhattisgarh | Power | 1,744.5 acres | Environmental approval granted | 7 Oct 2024 |
| Drilling of 22 Nos Boreholes for Proposed Hasdeo Bango Pumped Storage Hydro Electric… Lam Pahar P F, Korba, Chhattisgarh | Buildings & townships | 7,209.8 acres | Lapsed | 17 Sept 2024 |
| Dangari Pumped Storage Hydro-electric Project (1400 MW) Dangari, Jashpur, Chhattisgarh | Water & irrigation | 5,503.2 acres | Cleared for impact study | 6 Aug 2024 |
| Rouni Pumped Storage Hydro-electric Project (2100 MW) Bhadikona, Jashpur, Chhattisgarh | Water & irrigation | 5,598.8 acres | Cleared for impact study | 31 Jan 2024 |
| Dangari Pumped Storage Hydro-electric Project (1400 MW) Dangari, Jashpur, Chhattisgarh | Water & irrigation | 5,503.2 acres | Returned to applicant | 31 Jan 2024 |
| Hasdeo Bango Pumped Storage Hydro-electric Project (1200 MW) Lam Pahar P F, Korba, Chhattisgarh | Water & irrigation | 6,786.8 acres | Cleared for impact study | 20 Sept 2023 |
| 1 x 500 MW Coal Based Power Plant of M/s Chhattisgarh State Power Generation Company… Darri, Korba, Chhattisgarh | Power | 670.3 acres | Environmental approval granted | 14 Jun 2023 |
| Hasdeo Bango Pumped Storage Hydro-Electric Project (1200MW) Lam Pahar P F, Korba, Chhattisgarh | Water & irrigation | 7,121.3 acres | Returned to applicant | 26 May 2023 |
| Hasdeo Bango Pumped Storage Hydro Electric Project (1200 MW) Lam Pahar P F, Korba, Chhattisgarh | Water & irrigation | 6,409.1 acres | Under environmental review | 14 May 2023 |
| Proposed Expansion by addition of 2 x 660 MW Supercritical Units of Chhattisgarh State… Birbhat, Korba, Chhattisgarh | Power | 1,744.5 acres | Cleared for impact study | 9 Feb 2023 |
Chhattisgarh State Power projects by city
- CSChhattisgarh State Power in Korba16
- CSChhattisgarh State Power in Jashpur7
- CSChhattisgarh State Power in Gariaband4
Where Chhattisgarh State Power is building
- Korba, Chhattisgarh16
- Jashpur, Chhattisgarh7
- Gariaband, Chhattisgarh4
- Balrampur, Chhattisgarh2
- Raipur, Chhattisgarh1
Questions people ask
How many projects has Chhattisgarh State Power filed?
30 since January 2022, of which 13 are approved and 8 are awaiting a decision.
Where are Chhattisgarh State Power's projects?
Mostly in Korba, Chhattisgarh (16), Jashpur, Chhattisgarh (7), Gariaband, Chhattisgarh (4), Balrampur, Chhattisgarh (2) and Raipur, Chhattisgarh (1).
What did Chhattisgarh State Power file most recently?
Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking Exemption from Installation of Flue Gas Desulphurization (FGD) System for 1 x 500 MW and 2 x 660 MW Coal-Based Thermal Power Units of M/s Chhatisgarh State Power Generation Company Limited Under MoEF&CC Notification G.S.R 465 (E) dated 11th July 2025 in Darri, Korba, filed on 16 Nov 2026. Status: Under environmental review.
About this information
Compiled from publicly available approval records, grouped by the applicant's registered name. What is Developing? is not affiliated with Chhattisgarh State Power; the badge is generated from its name. Group companies that file under different names may appear on separate pages. Statuses can change between our updates; check with the authority before making decisions. Spotted a mistake? Tell us.