Quick answers
What is this project?
Enhancement of MS Ingot/Billet production from 58,360TPA to 168,000TPA, through replacement of existing 3x10T IF with 3x12T IF and installation of additional 1x12T IF, Installation of rolling mill for production of 156000TPA Rolled Products and 1x4MVA + 1x2.5MVA Submerged Arc Furnace for Production of 16,300TPA Ferro Alloys (max.) or 27,300TPA Pig Iron or combination of any by M/s Shree Banke Bihari Ispat Pvt. Ltd. at OP Jindal Industrial Park, Punjipathra, Tamnar, Raigarh, Chhattisgarh is an approved industrial project in Tum\D\H, Gharghoda, Raigarh, Chhattisgarh. The site covers 4.9 acres.
Who is building it?
The applicant is Shree Bankebihari Ispat Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 19 Oct 2024), as of 27 Nov 2026.
Where is it?
In Tum\D\H, Gharghoda, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹28.7 crore and a site of 4.9 acres.
When was it filed?
The application was filed on 26 Jul 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 19 Oct 2024 |
| Application filed | 26 Jul 2024 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Shree Bankebihari Ispat Private Limited |
| Land area | 4.9 acres (2 ha) |
| Project cost | ₹28.7 crore |
| Village / locality | Tum\D\H |
| Taluk / tehsil | Gharghoda |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02230 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 4.9 acres, this one is smaller than 94% of them.
21 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Tum\D\H, Gharghoda, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environment Clearance from M/s. SHRI NIRMALANAND STEELS CASTING… — lapsed, 200 m away
- Expansion of the Existing Integrated Steel Plant — environmental approval granted, 1.4 km away
- Expansion of the Existing Integrated Steel Plant — cleared for impact study, 1.4 km away
- Diversion of Forest land for non-forest purpose under Forest Conservation Act,… — lapsed, 1.7 km away
- Diversion of Forest land for non-forest purpose under Forest Conservation Act,… — lapsed, 1.7 km away
- 15 MT x 2 Nos of induction furnace — environmental approval granted, 2.6 km away
- Laying of 33KVA Dedicated Line Banjari to Punjipathra — lapsed, 2.6 km away
- Raigarh-Gharghoda — lapsed, 3.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.