What is this project?
Request for Amendments to Environmental Clearance (Ec) Comprising of Change in Cfbc Based Power Plant From 2 X 250 MW to 2 X 125 MW (Phase # 1) & 1 X 250 MW (Phase # 2) and Request for Permission for Utilisation of Harvested Rain Water From Existing Natural Ponds & Water Reservoirs Within the Site for Phase-1 Operations & Remaining Phases Will Be Through Kelo River, for Nr Iron and Power Private Limited is an approved industrial project in Sivpuri, Raigarh, Chhattisgarh. The site covers 738.9 acres.
Who is building it?
The applicant is Nr Iron and Power Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 30 Nov 2025), as of 27 Nov 2026.
Where is it?
In Sivpuri, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹8,917 crore and a site of 738.9 acres.
When was it filed?
The application was filed on 4 Oct 2025.
Project details
| Official title | Request for Amendments to Environmental Clearance (Ec) Comprising of Change in Cfbc Based Power Plant From 2 X 250 MW to 2 X 125 MW (Phase # 1) & 1 X 250 MW (Phase # 2) and Request for Permission for Utilisation of Harvested Rain Water From Existing Natural Ponds & Water Reservoirs Within the Site for Phase-1 Operations & Remaining Phases Will Be Through Kelo River, for Nr Iron and Power Private Limited Located at Shivpuri Village, Raigarh Tehsil & District, Chhattisgarh |
|---|---|
| Status | Environmental approval granted |
| Status since | 30 Nov 2025 |
| Application filed | 4 Oct 2025 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Nr Iron and Power Private Limited |
| Land area | 738.9 acres (299 ha) |
| Project cost | ₹8,917 crore |
| Village / locality | Sivpuri |
| Taluk / tehsil | Raigarh |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-02387 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 738.9 acres, this one is larger than 92% of them.
51 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sivpuri, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Integrated Steel Plant - Iron Ore Beneficiation Plant (1 x 5.2 MTPA, Pellet… — environmental approval granted, 0 m away
- Integrated Steel Plant - Iron Ore Beneficiation Plant (1 x 5.2 MTPA, Pellet… — cleared for impact study, 0 m away
- Approach Road — lapsed, 1.1 km away
- Approach Road — lapsed, 1.1 km away
- 132KV Transmission Line from CSPTCL 220/132/33KV Substation Gerwani to M/s… — lapsed, 1.1 km away
- Regularization of existing and operating Reheating Furnace based rolling mill… — cleared for impact study, 1.3 km away
- 132 KV DCSS transmission line from CSPTCL 220/132 KV S/s Gerwani to M/s… — lapsed, 1.4 km away
- Regularization of Reheating Furnace based rolling mill for Chandrahasni Ispat… — lapsed, 1.4 km away
More from Nr Iron and Power Private Limited in Raigarh
- Integrated Steel Plant - Iron Ore Beneficiation Plant (1 x 5.2 MTPA, Pellet… — environmental approval granted
- Integrated Steel Plant - Iron Ore Beneficiation Plant (1 x 5.2 MTPA, Pellet… — cleared for impact study