Quick answers
What is this project?
Expansion of Grain Based Distillery Plant from 100 KLD to 300 KLD (300 KLD Bio-Ethanol or 200 KLD Bio-Ethanol + 100 KLD ENA or 100 TPD derivatives i.e Ethyl/ Methyl/ Butyl Acetates, Bio Acetic Acid/ Crotanaldehyde/ Bio Butanol) with Co-generation Power Plant from 3 MW to 12 MW by M/s Aarti Synergy Private Limited is a lapsed industrial project in Dande Kalan, Raipur, Chhattisgarh. The site covers 30.3 acres.
Who is building it?
The applicant is Aarti Synergy Private Limited.
Has it been approved?
No. The application was lapsed on 1 Aug 2026, so it is no longer under consideration.
Where is it?
In Dande Kalan, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹3.8 crore and a site of 30.3 acres.
When was it filed?
The application was filed on 27 Jun 2026.
Project details
| Official title | Expansion of Grain Based Distillery Plant from 100 KLD to 300 KLD (300 KLD Bio-Ethanol or 200 KLD Bio-Ethanol + 100 KLD ENA or 100 TPD derivatives i.e Ethyl/ Methyl/ Butyl Acetates, Bio Acetic Acid/ Crotanaldehyde/ Bio Butanol) with Co-generation Power Plant from 3 MW to 12 MW at Village - Dondekala, Tehsil & District – Raipur, Chhattisgarh by M/s Aarti Synergy Private Limited |
|---|---|
| Status | Lapsed |
| Status since | 1 Aug 2026 |
| Application filed | 27 Jun 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Aarti Synergy Private Limited |
| Land area | 30.3 acres (12.3 ha) |
| Project cost | ₹3.8 crore |
| Village / locality | Dande Kalan |
| Taluk / tehsil | Raipur |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-03588 |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 30.3 acres, this one is larger than 53% of them.
128 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Dande Kalan, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Dondekala Limestone Quarry (Area -2.687) — cleared for impact study, 1.3 km away
- Jayanti Lal Patel — lapsed, 1.5 km away
- Jayanti Lal Patel — environmental approval granted, 1.5 km away
- Expansion of Steel Plant–Sponge Iron-60000 to 290000 TPA),MS Ingots/… — under environmental review, 2.2 km away
- Lalpur Limestone Mine Proprietor Harshit Sharma — environmental approval granted, 2.4 km away
- Limestone Quarry Village Matiya Area-2.00 Acre Project Proponent Gaytri Stone… — lapsed, 2.5 km away
- Akhilesh Kumar Singh -Lalpur Limestone Mine — environmental approval granted, 2.6 km away
- Kamlesh Bhawnani — lapsed, 2.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.