Quick answers
What is this project?
Land diversion for construction of 132/33 KV Substation Saraipali Distt. Raigarh is a lapsed power project in Sivpuri, Raigarh, Chhattisgarh. The site covers 0.3 acres.
Who is building it?
The applicant is Mohit Banjare.
Has it been approved?
No. The application was lapsed on 27 Apr 2025, so it is no longer under consideration.
Where is it?
In Sivpuri, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹45 lakh; a site of 0.3 acres and 2,310 m² of forest land.
When was it filed?
The application was filed on 9 Oct 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 27 Apr 2025 |
| Application filed | 9 Oct 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Mohit Banjare |
| Land area | 1,300 m² |
| Forest land | 2,310 m² |
| Project cost | ₹45 lakh |
| Village / locality | Sivpuri |
| Taluk / tehsil | Raigarh |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-03764 |
In context
29 applications in Raigarh since January 2022 are in the same category (Power): 13 approved, 9 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 0.3 acres, this one is smaller than 100% of them.
47 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sivpuri, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 132KV DCSS transmission line radiating from CSPTCL 220/132 KV Substation… — in-principle approval, conditions pending, 450 m away
- Proposed Change in Induction Furnaces Configuration From 3 X 15 T As Per Ec to… — initial checks, 550 m away
- Approach Road — lapsed, 600 m away
- Approach Road — lapsed, 600 m away
- Change in name from S S Steel & Power to S.S. STEELS & POWER PRIVATE LIMITED… — lapsed, 600 m away
- Diversion of Revenue Forest Land in Villages Chiraipani and Gerwani, Range… — not approved, 650 m away
- Request for issue of Amendments to the Environmental Clearance (EC) issued to… — more information requested, 700 m away
- Transfer of Environment Clearance from M/s. Salasar Steel and Power Ltd. to… — under environmental review, 700 m away
More from Mohit Banjare in Raigarh
- Proposed 132/33 KV SUB-STATION Medical college — forest land use approved
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.