What is this project?
Environment Clearance for Proposed Addition / Alteration in Maha Laxmi Castle and Villas Private Limited in Bakoli, Alipur, G.T. Karnal Road At Delhi is an approved commercial project in Bakoli, Alipur, North, Delhi. It plans 182 units of up to 7 floors on 5.2 acres.
Who is building it?
The applicant is Mahalaxmi Castles and Villas Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 22 Apr 2026), as of 27 Nov 2026.
Where is it?
In Bakoli, Alipur, North, Delhi.
How big is it?
It has a stated cost of ₹86.4 crore and a site of 5.2 acres.
When was it filed?
The application was filed on 19 Mar 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 22 Apr 2026 |
| Application filed | 19 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Mahalaxmi Castles and Villas Private Limited |
| Use | Commercial |
| Units | 182 |
| Floors (tallest) | 7 |
| Basements | 1 |
| Height | 46 m |
| Parking spaces | 385 |
| Land area | 5.2 acres (2.1 ha) |
| Built-up area | 19,964 m² (2,14,890 sq ft) |
| Plot area | 24,657 m² (2,65,405 sq ft) |
| Project cost | ₹86.4 crore |
| Village / locality | Bakoli |
| Taluk / tehsil | Alipur |
| District | North |
| State | Delhi |
| Location from | Site boundary on record |
| Our reference | WID-DL-00048 |
In context
19 applications in North since January 2022 are in the same category (Buildings & townships): 17 approved, 2 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 5.2 acres, this one is larger than 63% of them.
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bakoli, Alipur, North, Delhi. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 'Construction of Warehouse' by Jindpur Industrial Park Private Limited. — under environmental review, 3.3 km away
- Noc for tree cutting at Railway Land Parcel at Ashok Vihar, Delhi, Village-… — not approved, 3.8 km away
- Ewaste Ecopark - 2 — lapsed, 3.9 km away
- Providing & Laying 300 Mm to 1400 Mm Dia Internal and Peripheral Sewer Line in… — more information requested, 4 km away
- Removal of trees obstructing the main carriageway along the Left Bank of Drain… — initial checks, 5 km away
- 200 Nos Tube Wells in Flood Plains of Palla and Other Suitable Locations for… — more information requested, 5.1 km away
- Construction of Rithala - Kundli Metro Corridor Of DMRC Phase- IV MRTS — forest land use approved, 5.3 km away
- Removal of LILO of Bawana- Mandola 400kV D/C line at Maharanibagh S/S and… — forest land use approved, 5.8 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.