Quick answers
What is this project?
Diversion of Forest Land for the laying of Underground 11 KV Electric Feeder Line from M/s Silvassa Bottling Company,Dapada to Khadoli Substation is a lapsed power project in Dapada, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu. It seeks 0.3 acres of forest land.
Who is building it?
The applicant is Silvassa Bottling Co.
Has it been approved?
No. The application was lapsed on 22 Apr 2023, so it is no longer under consideration.
Where is it?
In Dapada, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu.
How big is it?
It has a stated cost of ₹1 crore and 1,150 m² of forest land.
When was it filed?
The application was filed on 22 Apr 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 22 Apr 2023 |
| Application filed | 22 Apr 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Silvassa Bottling Co |
| Forest land | 1,150 m² |
| Project cost | ₹1 crore |
| Village / locality | Dapada |
| Taluk / tehsil | Dadra & Nagar Haveli |
| District | Dadra & Nagar Haveli |
| State | Dadra and Nagar Haveli and Daman and Diu |
| Location from | Site boundary on record |
| Our reference | WID-DN-00115 |
In context
18 applications in Dadra & Nagar Haveli since January 2022 are in the same category (Power): 7 approved, 2 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 15 months from filing to approval.
25 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Dapada, Dadra & Nagar Haveli, Dadra and Nagar Haveli and Daman and Diu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of Protected Forest Land for the Laying of Underground 11KV Electric… — lapsed, 0 m away
- Diversion of Forest Land for the Laying of Underground 11KV Electric Feeder… — lapsed, 50 m away
- Diversion of Forest Land (WLS) for Widening and Strengthening of Road Stretch… — under wildlife review, 750 m away
- Gas Distribution Network in DNH GA (Vasona Char Rasta to Khanvel Petrol Pump… — forest land use approved, 1 km away
- Mining project by Shri Shyam Infrsolutions Pvt. Ltd. — lapsed, 1.9 km away
- Mining project by Shri Shyam Infrasolutions Pvt. Ltd. — lapsed, 2 km away
- Mining project by Shri Shyam Infrasolutions Pvt. Ltd. — lapsed, 2 km away
- Himalaya Infra — lapsed, 2 km away
More from Silvassa Bottling Co in Dadra & Nagar Haveli
- Diversion of Protected Forest Land for the Laying of Underground 11KV Electric… — lapsed
- Diversion of Forest Land for the Laying of Underground 11KV Electric Feeder… — lapsed
All 3 Silvassa Bottling Co projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.