What is this project?
Iron Ore Dump Handling at 'DUMP NO. 15' (E Auctioned Mine Dump), for production of saleable output (after dry screening and crushing) of 2.0 MTPA with maximum annual excavation of 3.703 MTPA, spread over an area of 19.01Ha., located at Survey No. 48/0(P), 49/0(P), 50/0(P), 51(P), 52(P), 53(P) and 54(P) of Bandoli village, Dharbandora Taluka, Kushavati District (erstwhile South Goa District) Goa State, of M/s KAI International Private Limited is a proposed mining project in Bandoli, Dharbandora, South Goa, Goa. The site covers 47 acres.
Who is building it?
The applicant is K a I International Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Bandoli, Dharbandora, South Goa, Goa.
How big is it?
It has a stated cost of ₹85 crore and a site of 47 acres.
When was it filed?
The application was filed on 28 Oct 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 21 Nov 2026 |
| Application filed | 28 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | K a I International Private Limited |
| Land area | 47 acres (19 ha) |
| Project cost | ₹85 crore |
| Village / locality | Bandoli |
| Taluk / tehsil | Dharbandora |
| District | South Goa |
| State | Goa |
| Location from | Site boundary on record |
| Our reference | WID-GA-00409 |
In context
67 applications in South Goa since January 2022 are in the same category (Mining): 36 approved, 23 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 47 acres, this one is larger than 75% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 108.5 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 21 mining leases have applied within 5 km.
Where it is
Bandoli, Dharbandora, South Goa, Goa. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Iron Ore Dump Handling at 'DUMP NO. 15' (E Auctioned Mine Dump), located at… — returned to applicant, 50 m away
- Iron Ore Dump Handling at Dump-14, located in Survey No. 38/2(P) of Cormonem… — initial checks, 750 m away
- Handling of Iron Ore dump Situated Outside the Lease Area on Private property… — environmental approval granted, 750 m away
- Augmentation of Khandepar River by Pumping of Water From Abandoned Mining Pit… — lapsed, 950 m away
- Enhancement of Iron Ore Wet Beneficiation Plant from 0.64 Million TPA (0.914… — cleared for impact study, 1.3 km away
- Enhancement of Iron Ore Wet Beneficiation Plant from 0.64 Million TPA (0.914… — environmental approval granted, 1.3 km away
- Proposed Enhancement in Production Capacity of Basalt Stone & Murrum Quarry… — environmental approval granted, 1.9 km away
- Proposed Basalt Quarry bearing lease no. 04/Basalt/90 & 03/Basalt/07 (renewed… — environmental approval granted, 2 km away
More from K a I International Private Limited in South Goa
- Iron Ore Dump Handling at 'DUMP NO. 15' (E Auctioned Mine Dump), located at… — returned to applicant
All 5 K a I International projects across India
About this information