What is Developing? Open the mapMap

More information requestedBuildings & townships · Ahmadabad, Gujarat

Royal Crown

Royal Crown is a proposed building project in Khodiyar, Daskroi, Ahmadabad, Gujarat. The site covers 1.2 acres. Its stated project cost is ₹61.2 crore. As of 27 Nov 2026, its status is “More information requested” (since 3 Aug 2023).

See it on the live map All projects in Ahmadabad

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusMore information requested
Status since3 Aug 2023
Application filed3 Aug 2023
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantUmiya Buildcon
Land area1.2 acres (0.5 ha)
Project cost₹61.2 crore
Village / localityKhodiyar
Taluk / tehsilDaskroi
DistrictAhmadabad
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-01813

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 8 Jan 2024Lapsed1.2 acres₹50.9 crore
New project filed 3 Aug 2023 (this page)More information requested1.2 acres₹61.2 crore

What the filings say

What is planned

Umiya Buildcon proposes the construction of Royal Crown, a mixed-use residential and commercial development. According to the applicant's project report, the complex will feature 172 residential units and 18 commercial shops. The project is designed with multiple building blocks reaching a maximum height of 14 floors above a ground level and three basement levels.

The total plot area for the development is 4,796.00 sq. m. (0.48 hectares or 1.18 acres). While initial conceptual plans stated a total built-up area of 29,248.21 sq. m., a revised layout plan filed by the applicant indicates an expanded total built-up area of 39,374.77 sq. m.

Layout and design

The site layout includes a common plot area of approximately 497.38 sq. m. for society members' use. The ground floor is planned to accommodate the 18 commercial shops, society common amenities, and dedicated electric meter rooms. The residential units are distributed across the upper 14 floors.

The three basement levels are designated for parking and services. The project includes a 6.00-metre-wide approach road and internal pathways designed with a 1:12 slope for accessibility. Solar calculations included in the master plan indicate that the project will provide approximately 43.00 sq. m. of solar energy installations to support the development's requirements.

Land and surroundings

The project site is located in Khodiyar village, within the Ahmedabad Municipal Corporation limits. A geotechnical investigation report based on five boreholes drilled to a depth of 40.0 metres describes the subsoil profile as yellowish-brown silty clayey sand and sandy clays of intermediate plasticity. During the investigation conducted in March 2023, the ground water table was encountered at depths ranging from 22.10 metres to 22.60 metres.

Water, power and access

The applicant states that water for the project will be sourced from the Narmada water supply through the Ahmedabad Municipal Corporation (AMC). If groundwater extraction is required, the applicant intends to obtain necessary permissions from the Central Ground Water Authority (CGWA).

Power will be sourced from Uttar Gujarat Vij Company Limited (UGVCL). The estimated power requirement is 30 kW during the construction phase and approximately 2.0 MW during the operational phase. The site is accessed via a 36.00-metre-wide Town Planning Scheme (TPS) road.

Environmental safeguards

The project documents outline several environmental management measures:

ItemDetail
Plot Area4,796.00 sq. m. (0.48 hectares)
Total Built-up Area (Revised)39,374.77 sq. m.
Residential Units172
Commercial Units (Shops)18
Tallest Building3 Basements + Ground + 14 Floors
Water SourceAMC (Narmada Water)
Operational Power2.0 MW
Tree Plantation120 trees provided

Royal Crown site plan and layout

3 drawings from the project's filings. Sign in free to see them.

Royal Crown: Site layout: building blocks, approach roads and common plot (preview)🔒 Sign in free to see it
Site layout: building blocks, approach roads and common plot
Royal Crown: Revised layout plan: FSI and built-up area tables (preview)🔒 Sign in free to see it
Revised layout plan: FSI and built-up area tables
Royal Crown: Borehole location plan for geotechnical investigation (preview)🔒 Sign in free to see it
Borehole location plan for geotechnical investigation

In context

1,175 applications in Ahmadabad since January 2022 are in the same category (Buildings & townships): 916 approved, 201 filed or under review, and 58 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.2 acres, this one is smaller than 73% of them.

120 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Khodiyar, Daskroi, Ahmadabad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.