What is Developing? Open the mapMap

Environmental approval grantedBuildings & townships · Surat, Gujarat

Shree Hari Solitaire

Shree Hari Solitaire is an approved building project in Dindoli, Majura, Surat, Gujarat. The site covers 1.3 acres. Its stated project cost is ₹31 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 9 Dec 2023).

See it on the live map All projects in Surat

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is Shree Hari Solitaire?

Shree Hari Solitaire is an approved building project in Dindoli, Majura, Surat, Gujarat. The site covers 1.3 acres.

Who is building it?

The applicant is Varni Enterprise.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 9 Dec 2023), as of 27 Nov 2026.

Where is it?

In Dindoli, Majura, Surat, Gujarat.

How big is it?

It has a stated cost of ₹31 crore and a site of 1.3 acres.

When was it filed?

The application was filed on 9 Dec 2023.

Project details

StatusEnvironmental approval granted
Status since9 Dec 2023
Application filed9 Dec 2023
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantVarni Enterprise
Land area1.3 acres (0.5 ha)
Project cost₹31 crore
Village / localityDindoli
Taluk / tehsilMajura
DistrictSurat
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-02064

What the filings say

What is planned

Shree Hari Solitaire is a residential and commercial development proposed by Varni Enterprise. The project is planned on a plot of 0.52 hectares (1.28 acres) and consists of two main building blocks, designated as A1/A2 and B1/B2.

The applicant's project report specifies a total of 172 units, comprising:

The buildings are designed with a basement, a ground floor, and 10 upper floors, reaching a total height of 35.06 metres. The total built-up area is 22,929.33 square metres. A small temple occupying 15.68 square metres is also planned within the common plot area.

Layout and design

The site layout features two parallel building wings separated by a central open space and internal access roads. The ground floor is dedicated to commercial shops and building foyers, while the upper floors house the residential apartments.

Parking is distributed across the basement, ground level, and hollow plinth areas. The project provides a total of 4,541.78 square metres for parking, accommodating 152 four-wheelers and 526 two-wheelers. This includes dedicated spaces for visitors, representing approximately 10% of the total Floor Space Index (FSI).

Land and surroundings

The project is located at Final Plot No. 61/B in Dindoli, Surat. The site is bordered by a 24-metre wide road to the south. Surrounding plots include residential and commercial zones, with a water distribution centre and a garden located in the immediate vicinity. The net plot area is 5,170 square metres.

Water, power and access

Water requirements will be met through the Surat Municipal Corporation (SMC) supply. For wastewater management, the applicant proposes a 100 kilolitres per day (KLD) Sewage Treatment Plant (STP) using Membrane Bioreactor (MBR) technology. Treated sewage will be discharged into the SMC drainage system.

Power will be sourced from the local grid. A Diesel Generator (DG) set with acoustic enclosures will be installed for emergency backup. To promote renewable energy, the applicant plans to install a 50 KW rooftop solar system, requiring approximately 300 square metres of terrace space.

Environmental safeguards

The Environmental Management Plan (EMP) includes a total capital expenditure of ₹1.95 crore. Key components include:

Project Figures

ItemDetail
Total Built-up Area22,929.33 sq. m.
FSI Area13,955.76 sq. m.
Ground Coverage1,786.37 sq. m.
Residential Units160 Flats
Commercial Units12 Shops
Total Parking Area4,541.78 sq. m.
STP Capacity100 KLD
Solar Power50 KW
EMP Capital Cost₹1.95 crore
CER Budget (2%)₹0.62 crore

Shree Hari Solitaire site plan and layout

4 drawings from the project's filings. Sign in free to see them.

Shree Hari Solitaire: Site layout: building blocks, internal roads, and temple location (preview)🔒 Sign in free to see it
Site layout: building blocks, internal roads, and temple location
Shree Hari Solitaire: Floor plans: typical residential layout and ground floor shops (preview)🔒 Sign in free to see it
Floor plans: typical residential layout and ground floor shops
Shree Hari Solitaire: Building elevation and cross-section showing 10 floors and basement (preview)🔒 Sign in free to see it
Building elevation and cross-section showing 10 floors and basement
Shree Hari Solitaire: Parking layout plan for basement and ground levels (preview)🔒 Sign in free to see it
Parking layout plan for basement and ground levels

In context

489 applications in Surat since January 2022 are in the same category (Buildings & townships): 376 approved, 79 filed or under review, and 34 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.3 acres, this one is smaller than 66% of them.

55 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Dindoli, Majura, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.